| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2006 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* | |
| 06/09/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PRESSURE TEST OK ON GAS PROVIDE SEDIMENT TRAP AT WATER HEATER INSTALL AGA VALVE AT STOVE WITH FLEX INSTALL PIPE COVERING ON OUTSIDE PIPES |
|
| 06/02/2006 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 05/22/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PRESSURE TEST REQUIRED. USE 15 PSI GAUGE. IF WATER HEATER IS GOING TO BE REPLACED -ADD TO PERMIT TYPE B VENT REQUIRED. T&P SHALL TERMINATE 6"-24" ABOVE GROUND. FLUE VENTS WITHIN 10' OF COOLER SHALL BE EXTENDED TO 3' ABOVE COOLER. AGA VALVES REQUIRED ELECTRICAL BONDING REQUIRED. |