Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T06PL00832
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/19/2007 | SITE - SEWER | Approved | IVRS - Inspection :* | |
09/21/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* (SPARK) TEST #1, #2, OK VACUUM TEST #3, #4, #5, #6 OK NEED AUTHORIZATION TO DISCHARGE FOR FINAL. |
|
08/21/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #6 4" HCS TO EAST AIRTEST OK FROM MANHOLE #6 4" HCS TO WEST AIRTEST OK FROM MANHOLE #5 4" HCS TO WEST AIRTEST OK FROM MANHOLE #5 4" HCS TO SOUTHEAST AIRTEST OK FROM MANHOLE #4 4" HCS TO SOUTH AIRTEST OK FROM MANHOLE #3 4" HCS TO EAST AIRTEST OK FROM MANHOLE #3 4" HCS TO WEST AIRTEST OK FROM MANHOLE #5 TO MANHOLE #6 8" SDR AIRTEST OK FROM MANHOLE #5 TO MANHOLE #4 8" SDR AIRTEST OK FROM MANHOLE #2 TO MANHOLE #3 8" SDR AIRTEST OK FROM MANHOLE #3 TO MANHOLE #4 8" SDR AIRTEST OK FROM MANHOLE EXISTING PUBLIC TO #1 8" SDR AIRTEST OK FROM MANHOLE #1 TO MANHOLE #2 8" SDR AIRTEST OK |
|
08/08/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE STACKED, 4" HCS LATERALS FROM MANHOLES, BEDDING, LAYING, TRACER, SHADING OK SEE NOTES FROM 7/19/06 INSPECTION FOR TESTING OF PIPING & MANHOLES & PCDEQ APPROVAL |
|
08/04/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE BASES POURED OK 4" LATERALS CONTINUE FROM MANHOLES. |
|
08/02/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #3 4" TO S-8, 4" TO S-9, 8" TO MANHOLE #4 FROM MANHOLE #4 4" TO S-8, 8" TO MANHOLE #5 1. NEED DETAIL #108 PCWWM FOR 315 SEWER WATER CROSSING FROM MANHOLE #5 4" STUBS ONLY FOR S-8 & S-10 FROM MANHOLE #5 8" TO MANHOLE #6 FROM MANHOLE #6 4" STUBS ONLY FOR S-22 & S-23 BEDDING, LAYING, TRACER, SHADING OK EXCEPT NOTE 1 |
|
07/27/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #2 TO MANHOLE #3 BEDDING, LAYING, TRACER, SHADING OK |
|
07/21/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM EXISTING MANHOLE #16 TO MANHOLE #1 8" SDR 35 BEDDING, LAYING, SHADING, TRACER OK FROM MANHOLE #1 TO MANHOLE #2 BEDDING, LAYING, SHADING, TRACER OK |
|
07/19/2006 | SITE - SEWER | Partial Approval | IVRS - Inspection :* HOLD OVER TO 7/16/06 PER CONTRACTOR 8" SDR 35 FROM EXISTING MANHOLE #6 PUBLIC APPROX. 22' SOUTH BEDDING, LAYING, TRACER, SHADING, OK PCDEQ OK OK PLAN. THIS PROJECT TO BE INSPECTED BY C.O.T & SPECIAL INSPECTOR FOR PCDEQ SHALL REQUIRE WITNESS OF PIPING, PIPE TESTING, MANHOLE VACUUM TESTING & AUTHORIZATION TO DISCHARGE FOR FINAL. |