Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/11/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* RECEIVED PUB CERTIFICATION |
|
| 05/10/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 05/09/2006 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* AFTER MEETING WITH CONTRACTOR THIS SYSTEM SHALL REQUIRE. 1. VACUUM BREAKER AT HOSE BIBB. 2. LANDSCAPING WATER SUPPLY REQUIRES MINIMUM PRESSURE VACUUM BREAKER WITH CERTIFICATION. 3. EXTEND TRACER WIRE WITH CORRECT WIRE CONNECTION INTO METER BOX. OK TO COVER REST OF DITCH. |
|
| 05/08/2006 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* SEE ALL NOTES FROM 5/5/06 INSPECTION. PIPING IS COVERED AT BUILDING CONNECTION AND APPEARS TO BE LEAKING. |
|
| 05/07/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* |