Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/12/2006 | ENGINEERING - FINAL | Approved | Per Dave Roberts, contractor does not needs to install gates on trash enclosure or strip ped. crossing on north side parking lot. | |
| 05/10/2006 | ENGINEERING - FINAL | Not ready for Inspection | Contractor completed HC ramp, per Dave Roberts. Contractor still needs to address items 4,6, and 8, per Dave Roberts. | |
| 03/30/2006 | ENGINEERING - FINAL | Denied | Punch List: 1- Install all H.C. ramps per C of T standard. 2- Install scuppers on roof drains. 3- Install sidewalk scupper per note 25 on approved plans. 4- adjust irrigation box flush with top of sidewalk. (sticks up 6 inches) 5- Install basin inlet per approved drawings. 6- Install gates and bollards for trash enclosure. Per approved drawings. 7- Install 8' sidewalk around perimeter of building. per approved plans. 8- complete all parking lot striping. |