Case: T06DV00624

Parcel: 11706168C


Addresses:

318 E CONGRESS ST


Inspection Status: Approved

Inspection History: INSP - FOLLOW UP CODE ENFORCE

Case Number - T06DV00624

Inspection Description - INSP - FOLLOW UP CODE ENFORCE

Inspection Status - Approved

Date Description Inspector Results Comments
06/22/2006 INSP - FOLLOW UP CODE ENFORCE Approved VISITED SITE, CHECKED WITH SABINO ELECTRIC SUPERINTENDENT, BOBBY, WHO MENTIONED SABINO WOULD BE COMPLETING THE ELECTRICAL TODAY BY THE END OF THE BUSINESS DAY. SERVICE PANEL FROM THE PEDESTEL WAS BEING INSTALLED AT THE TIME OF INSPECTION & VERY NEAR COMPLETION. SPOKE WITH MARTY OF ACM WHO MENTIONED THE PLUMBING OR PIPING WAS GOING SLOW, BUT HE EXPECTED TO HAVE THE EAST SECTION COMPLETED & WOULD BE STARTING THE 2ND OR WEST SECTION THIS AFTERNOON. AN ADDITIONAL PERSON WAS HELPING MARTY WITH THE PLUMBING & 2-3 MORE PEOPLE HELPING SET THE DUCT WORK ALSO MOVING ALONG SLOWER THAN EXPECTED. WILL FOLLOW UP LATE THIS AFTERNOON FOR PROGRESS CHECK. FEW PICTURES WERE TAKEN.
06/22/2006 INSP - FOLLOW UP CODE ENFORCE Approved VISITED SITETOOK INSPECTOR JERRY ORTA TO GO OVER ELECTRICALAND TO EXPLAIN TO ME ALL PORTIONS OF ELETRICAL. UPON ARRIVAL FOUND DSD ON SITE TO INSPECT THE ELECTRICAL.DSD INSPECTOR CHARLIE CLEMONS DID FIND SECERAL ISSUES REJECTED THE INSPECTION. INSPECTION WAS RE-CALLED FOR TOMORROW 6/23. SABINO ELECTRIC MIKE BARNES MENTIONED ALL CORRECTIONS WIL BE MADE AND READY FOR THE FOLLOWING DAY TEP WALTER YOSIN WAS ON SITE TO ALSO EXPLAINED TO SABINO WAHT WAS NEEDED FOR TEP TO TURN ON POWER.
* STEVE ROGERS TOOK ME UP TO ONE OF THE AIR HANDLERS AND SHOWED ME A CRACK IN ONE OF THE COILS MENTIONED CRACK WAS FOUND WHEN TRYING TO CHARGE THE LINES, PROBOBLY CRACKED DURING SHIPPING STEVE MENTIONED THEY WOULD WELD THE CRACK AND REORDER THE PART REINSTALL AT A LATER DATE. NO PICTURES TAKEN. DSD REPORT WILL BE IN FILE. WILL FOLLOW UP WITH RICH DAVES BY E-MAIL.

06/23/06 VISITED SITE, MET MIKE BARNES SABINO ELECTIRC , AND CHARLIE CLEMONS DSD. CHARLIE CLEMONS RE-INSPECTED THE ELECTRICALAND FOUND MOST ISSUESFOUND N 6/22 HAD BEEN CORRECTED AND WAS ASKING SOME OTHER MINOR ISSUES BE CORRECTED AGAIN TODAY. INITIALLY MIKE BARNES BECAME VERY UPSET, SETTLED DOWN AND MADE SURE ALL CORRECTIONS GET COMPLETED. SABINO ALREADY STARTED MAKING CORRECTIONS TEP WAS ON SITE TO CONNECT POWER. CHARLIE HAD OKED POWER AND MENTIONED HE WOULD BE BACK ON MONDAY 6/26 TO RE-INSPECT. SPOKE WITH STEVE ROGERS TO FIND OUT WHEN OR IF HE HAD CALLED FOR INSPECTIONS. STEVE MENTIONED MENTIONED HE WOULD NOT CALL UNTILL NEXT WEEK. STILL CONFIDENT UNIT WILL BE FIRED UP TODAY.
*RETURNED TO OOFICE UPDATED ELISCO AND DRAVES BY E-MAIL

WILL RETURN THIS PM TO BE SURE WORK IS COMPLETED.DSD INSPECTION REPORT IN CASE FILE.
06/21/2006 INSP - FOLLOW UP CODE ENFORCE Approved SPOKE WITH MIKE BARNES OF SABINO ELECTRIC & SUPERVISOR FOR THE RIALTO PROJECT. MIKE MENTIONED THAT ELECTRICAL WILL BE READY FOR THURSDAY AS SABINO WORKING ON THE SYSTEM TODAY WILL ALSO HAVE AN OVERNIGHT CREW WORKING THIS EVENING & A CREW TO FINISH UP TOMORROW. SABINO DID HAVE A SEVEN MEN CREW WORKING 3 SECTIONS OF THE SYSTEM AT ONE TIME. POWER WAS CUT TODAY A GENERATOR (60 KW) WAS PROVIDING POWER FOR THE DAY.
SPOKE WITH MARTY OF ACM WHO MENTIONED IN COMPLETING THE WORK & FIRING UNITS UP TOMORROW OR FRIDAY. MARTY DID FEEL 1/2 OR 1 UNIT COULD BE COMPLETED TODAY DUCT WORK INSTALLED TO THE EXISTING & NEW WORK INSIDE THE UNIT. MINOR CONNECTION PROBLEMS BEING WORKED OUT TODAY, HOWEVER WAS DISCOVERED EARLY THIS MORNING, CALLED IN RIGHT AWAY & NECESSARY PARTS BE BROUGHT OUT TODAY.
AGAIN SUPERVISORS OF ALL PHASES OF NEW CONSTRUCTION FEEL CONFIDENT THAT WORK WILL BE COMPLETED BY FRIDAY. PICTURES WERE TAKEN.
06/16/2006 INSP - FOLLOW UP CODE ENFORCE Approved VISITED SITE, UPON ARRIVAL FOUND MARCO CRANE ONSITE SETTING AIR HANDLERS ONTO THE ROOF ALONG WITH WEST UNITS. ONCE ON THE ROOF FOUND BONITA STEEL FINISHING THE WELDING OF PLATFORMS FOR A/C UNITS. SABINO ELECTRIC WAS ALSO ONSITE, HAD RUN MAJORITY OF CONDUCT FOR THE ELECTRIC TO UNITS. SABINO WAS MISSING THE DISCONNECTS FOR UNITS; ARE TO BE DELIVERED TUESDAY, 6/20/06, SABINO WILL BE THERE TO INSTALL BOXES & RUN WIRING.
STEVE RODGERS MENTIONED AIR HANDLERS ARE TO BE SET BY THE WEEKEND ALONG WITH FINAL DUCT WORK. UNITS ARE STILL SET TO BE FIRED UP BY 6/23/06. I WILL FOLLOW UP WITH INSPECTIONS ON WEDNESDAY & FRIDAY, 6/21/06 & 6/23/06. ACM HAS MADE GREAT PROGRESS. PICTURES WERE TAKEN.