Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/06/2008 | PLUMBING - FINAL | Approved | ||
| 10/03/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* 1. NO VALVES DOWNSTREAM OF AVB 2. DRAIN HOSE TO BE SECURED WITHIN 2" OF DRAINBOARD HEIGHT 3. NO MIXING VALVE OR ISOLATION VALVES FOR EYEWASH |
|
| 09/29/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PLUMBING FINAL IS COMPLETE, WITH EXCEPTION: SILVER RECOVERY UNIT - PHOTO LAB EQUIPMENT TO BE HOOKED UP FOR FINAL |
|
| 09/25/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 08/08/2008 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* FLOOR SINK RELOCATED PER REDLINE ON P1.1 WILL REQUIRE AUTHORIZATION FOR AAV AT THIS LOCATION OK TO COVER UNDERGROUND |