Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2007 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 01/11/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST RESTROOM FROM POINT OF CONNECTION EXISTING TO WYE AT 10' AFF REVENT HEIGHT PER REDLINE ON SITE. PIPE WRAPS OK. NEED TO SEE DEMO |
|
| 01/10/2007 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. SEE NOTES FROM 1/9/07 INSPECTION & COMPLY 2. FAILURE TO COMPLY SHALL RESULT IN REFEE. 3. ALL DEMO PIPING SHALL BE PERMANENT CAPPED WITH INSPECTION PRIOR TO LOWERING. 4. PROVIDE PIPE WRAPS FOR PIPING THRU CONCRETE. 5. NOT COMPLETE LIST. |
|
| 01/09/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1. VERTICAL X HORIZONTAL CHANGE OF DIRECTION TO BE A SWEEP 2. BRANCHES OVER FIVE FEET TO HAVE FULL SIZE CO |