Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2007 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 01/18/2007 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999* SEE NOTE #1 FROM 1/16/07 INSPECTION COMPLY WITH THIS REQUIREMENT OR YOU SHALL BE REFEED - PLANS CALLS FOR 1" INSULATION. |
|
| 01/16/2007 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* NOTE: SEE YOUR SHOCK STOP INSTALLATIONS INSTRUCTIONS HORIZONTAL OR VERTICAL INSTALLATION ONLY? 1. ALL INSULATION SHALL BE INSTALLED PER MANUFACTURE INSTALLATION INSTRUCTIONS. JOINTS TO BE SEALED WITH GLUE & RAGGING TAPE. INSULATION TO BE FULLY SURROUNDING PIPING & SEALED PROPERLY. SEE NOTE #17 PAGE P-4 FOR REQUIREMENTS. |
|
| 01/11/2007 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* WASTE & VENT THRU ROOF WATER TEST OK WATER PIPING OK 1. COMPLETE INSULATION ON ALL HOT & HOT RETURN PIPING AND PROVIDE SAFETY PLATES WHERE WITHIN 1 1/4" OF FACE OF STUD. PLUMBING OK TO DRYWALL AFTER ITEM #1 2. SHALL SEE COMPLETION OF EXISTING LAV FOR ADA ACCESS 3. CLOSET FLANGES REQUIRED TO BE 1 1/4" TOP OF FLANGE TO FINISH FLOOR SURFACE & SECURED TO FLOOR WITH WATER RESISTANT SCREWS - SEE INSTALLATION STANDARD #5 2003 UPC 4. ALL QUICK ACTING WATER VALVES REQUIRE WATER HAMMER ARRESTOR DEVICES EXAMPLE: WASHING MACHINE, FLUSH VALVES, SELENOID VALVES, DISHWASHER, ETC. |