Permit: T06CM05677

Parcel: 130140230


Addresses:

4220 E 22ND ST

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
03/17/2009 ENGINEERING - FINAL Approved -5 CLASS 1 BIKE LOCKERS ON SITE-PLAN CALLS OUT 6
Per phone conversation with David Rivera 132 spaces 4% is 5.28-5 class 1 bike lockers is acceptable
CP-132 PARKING SPACES REQ'D - NOT ENOUGH STRIPED ON SITE
CP-ALL TEMP STORAGE NEEDS TO BE PERMITTED OR REMOVED
CP-REMOVE ALL CONSTRUCTION DEBRIS FROM REAR LOT
03/16/2009 ENGINEERING - FINAL Correction Required WALKED SITE WITH MIKE WILHITE AND GLENN DABBS
-5 CLASS 1 BIKE LOCKERS ON SITE-PLAN CALLS OUT 6
-132 PARKING SPACES REQ'D - NOT ENOUGH STRIPED ON SITE
-ALL TEMP STORAGE NEEDS TO BE PERMITTED OR REMOVED
-REMOVE ALL CONSTRUCTION DEBRIS FROM REAR LOT
03/11/2009 ENGINEERING - FINAL Cancelled STRIPING WORK AND SOME SEAL COAT NOT COMPLETE
02/26/2009 ENGINEERING - FINAL Partial Approval PLZ HAVE CHANGES TO THE H/C PARKING LOCATION AND ADA ROUTE TO BUILDING APPROVED BY COT

FIELD VERIFIED -MEETS THE 2% SLOPE REQUIREMENTS
02/23/2009 ENGINEERING - FINAL Partial Approval SITE WORK CONTINUES NEAR ENTRANCE OFF OF COLUMBUS. CONTINUE MAINT. MEASURE TO MINIMIZE TRACKOUT ON BOTH COLUMBUS AND 22ND.
10/16/2008 ENGINEERING - FINAL Partial Approval 2 SITE VISITS

-CHANGING PUBLIC ACCESS
CONSTRUCTION AREA IS FENCED AND PUBLIC TRAFFIC IS ISOLATED
04/15/2008 ENGINEERING - FINAL Denied -NEED TO SEE PHASE PLAN
-H/C PARKING NOT INSTALLED
-ADA ACCESS FROM BACK LOT TO FRONT NOT COMPLETE-MISSING SIDEWALK
-SITE IS FENCED (PER AGREEMENT)
-CONSTRUCTION TRAFFIC ONLY SIGN IS UP (PER AGREEMENT)
04/15/2008 ENGINEERING - FINAL Partial Approval -NEED TO SEE PHASE PLAN-CP
-H/C PARKING INSTALLED ON WEST SIDE OF SITE SOUTH OF NEW SHOP
-ADA ACCESS FROM BACK LOT TO FRONT VIA WEST SIDE OF SITE
-SITE IS FENCED (PER AGREEMENT)
-CONSTRUCTION TRAFFIC ONLY SIGN IS UP (PER AGREEMENT)