Permit: T06CM05677

Parcel: 130140230


Addresses:

4220 E 22ND ST

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
03/17/2009 EXCAVATION/LAYOUT REBAR & ZON Approved
01/12/2009 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
17 (TOTAL) LIGHT POLE BASES REINFORCEMENT STEEL @ CORNER NORTHEAST DISPLAY LOT
11/17/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1 LIGHT POLE BASE ON EAST SIDE BY DRIVE
11/13/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
4 LIGHT POLE BASES @ N/E OF NEW BUILDING
08/29/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
3 LIGHT POLE BASES ON EAST SIDE NEXT TO SERVICE DRIVETHRU
08/12/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FIVE LIGHT POLE BASE RUNNING NORTH TO SOUTH
ALONG WEST SITE WALL -- OK TO POUR
08/08/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
7 ADDITIONAL LIGHT POLE BASES
CAISSONS @ NORTHWEST NEW CAR DISPLAY LOT
08/04/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
4 ADDITIONAL LIGHT POLE BASES AS NOTED ON SHEET C1.1
IN N/W PARKING AREAS

NOTE: DO NOT POUR N/W & N/E CORNER POLE BASES IN N/W NEW CAR DISPLAY LOT - FULL OF MUD & WATER
08/01/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
8 LIGHT POLE CAISSONS AS INITIALED ON TO BE APPROVED REVISED PLANS - 36" GALVANIZED 3/4 BOLTS 4" HOOK USED

1. PROVIDE DOCUMENTATION FOR MANUFACTURE
BOLT SIZE REG.
07/22/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
TWO ISOLATED COLUMN FOOTINGS #F-5 @ LINE 3/E.3 AND SITE WALL FOOTING RUNS N/S WEST AT SHOWROOM AND EAST TO WEST FROM SERVICE BAYS
06/12/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. C.5 TO (3) F10 FOOTING
C.5 AT 1, 1.5, 3 F3 & F4 FOOTING
2. F10 FOOTING 3 TO 5 G.1 TO I
F3 FOOTING AT G.1 - 3
3. (2) F7 FOOTING
F-4 FOOTING
LINE 1 D.9 E.6 6.1
05/28/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
APPROX. 250 LF BALANCE OF WEST SIDE SITE RETAINING WALL FOOTING EXCEPT NORTH END CAP
05/27/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
05/23/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
150 L.F OF RETAINING WALL FOOTING @ WEST SIDE
04/28/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
04/28/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
AFTER HRS. INSP. $150.00 PAID
BY MONEY ORDER #08-814507497

MONO FOOTING AT GRID LINE B.5 TO I/5 TO 7 -- OK TO POUR
04/25/2008 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELED
02/07/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PARTIAL APPROVAL @ GRID G9.7/7.1 - JAM FOOTING
01/25/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
(3) #F6 COLUMN FOOTINGS @ K/5.2, 6 & 7 AND DUMPSTER ENCLOSURE FOOTING @ S/W CORNER
01/22/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
F-10 & F-9
BUILDING FOOT @ RMS #178, 183 AND 186
INTERIOR CMU FOOTING @ GRID LINES D.3/7 TO 6.5 AND
6.5/C TO F AND COLUMN FOOTINGS @ 5/C.9 AND E.3
6/C.9 & E.3 AND G.1/6.7 & 6.5
01/17/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS & COLUMN FOOTINGS @ GRID LINES G.1/5 TO 5.5
5/E.6 TO F.3 - 5/1 TO 1.5 - B.7/5 TO7 - B/6.5 TO 7
7/G.9 TO G.9.5 - 7/G.9.9 TO I - I/7, 6.5, 6.2, 5.8, 5.2 TO 4 OK
01/16/2008 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
PERIMETER FOOTINGS @ SHOWROOM @
GRID LINES G.1/1 TO 1.8 - 1.1/F TO F.5 - 1.1/C.5 TO C.9 AND
C.5/1.1 TO 5
12/18/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
9 LIGHT POLE BASES @ SOUTH END OF SITE
(TWO ROWS OF 4 EACH) AND 1 @ EAST SIDE ACROSS FROM SERVICE BAYS
12/14/2007 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
NO APPROVED PLANS
10/29/2007 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
10/02/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
REINFORCEMENT STEEL @ FOOTINGS @ GRID LINES
9.3/A TO B - B/9.3 TO 11 - 11/A TO B & A/11 TO 9.3
09/28/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. PERIMETER WALL FOOTINGS @ GRID LINES 7/B TO G.9
B/7 TO NORTH OF COLUMN @ B/8 - H/7 TO 11
2. COLUMN FOOTINGS @ H/8 - B/7 - 7/B.7 - 7/C.9 - 7/D.9
7/E7.5, 7/G1 & 7/G9
2. COLUMN FOOTINGS @ H/8 - B/7
09/26/2007 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1. 5 - F1 COLUMN FOOTING @ 7/C - 7/D - 7/E - 7/F - 7/G
2. SITE WALL FOOTING ON SOUTH & WEST AS PER C1.2/AZ DETAIL
09/25/2007 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
NO SUPERINTENDENT ON SITE
NO PERMIT CARD ON SITE
09/13/2007 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
CONTRACTOR CANCELLED BY PHONE