Permit: T06CM05388

Parcel: 11005314J

Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T06CM05388

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
03/30/2007 PLUMBING - FINAL Approved IVRS - Inspection :*
03/28/2007 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
1. PAINT EXPOSED PLASTIC
2. INSTALL STRAINERS & GRATES ON FS
3. REMOVE FLOW CONTROL ON 3 COMP-SINK CONNECTED TO INTERCEPTOR.
4. SAFETY CABLE MUST BE SHORTER THAN SUPPLY FLEX TO GAS EQUIPT.
5. STEAM CHEF REQUIRES BACKFLOW PROTECTION
6. SUPPORT INDIRECT DRAINS. INSTALL PVC DRAIN LINES SO THAT HUB IS INCORRECT DIRECTION OF FLOW.
7. RECEIVED 4 BACKFLOW CERTS FOR BEVERAGE AND ICE EQUIPMENT.
8. TEMPERATURE LIMITING DEVICES FOR PUBLIC USE LAVS
03/22/2007 PLUMBING - FINAL Denied DO YOUR ROOF FLASHINGS MEET SPECIFICATIONS?
THEY DON'T APPEAR TO SEAL PROPERLY
ALSO, 1/2 COPPER CANNOT TOUCH METAL