Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T06CM05301
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/10/2008 | ENGINEERING - FINAL | Approved | ADDED REVISED SITE PLAN SHOWING CHANGE IN MAILBOX LOCATION AND LETTER FROM STAMPING AUTHORITY REGARDING THE REPAVING OF THE ENTIRE SITE AT THE END OF THE PROJECT | |
06/09/2008 | ENGINEERING - FINAL | Denied | COMPLETE ALL SITE WORK: NOT DONE-ALL ASPHALT PATCHES NEED TO BE COMPLETED PER COT STANDARDS CP-PATCH HOLES IN SOUTH PARKING LOT PER ARCHITECT CP COPIES NOT ON SITE-ADDRESS CHANGE TO MAILBOX LOCATION ON SITE PLAN CP-REMOVE BOLTS AND CONDUIT FOR PAY TELEPHONE LOCATION OR PLACE PHONE PER PLAN CP-ENSURE ALL CONSTRUCTION TRAFFIC IS SEPARATED FROM PUBLIC ACCESS AREAS (N AND S SIDE OF BUILDING) NO ACCESS TO CURRENT MAILBOX LOCATION CP-REMOVE ALL CONSTRUCTION DEBRIS, MATERIALS AND TOOLS FROM PUBLIC AREAS IN PROGRESS-CLEAN UP NEW WASH OUT IN PARKING AREA (SOUTH SIDE) WEST OF MAILBOXES NOT ON SITE-PLEASE HAVE CHANGE TO MAILBOX LOCATIONS STAMPED PLAN SET AVAILABLE AT INSPECTION CP-REMOVE EXTRA PARKING STOP AT WEST SIDE OF PARKING LOT AND PLACE WHEEL STOP IN H/C SPOT CP SECURITY TRAILER TO BE MOVED-REMOVE ELECTRIC EXTENSION CORD FROM POOL AREA TO SECURITY TRAILER MET WITH PHIL CARHUFF HE WILL SUPPLY LETTER THAT ASPHALT PATCHES ARE TEMPORARY AND RESURFACING/PAVING WILL BE COMPLETED IN FUTURE PHASES |
|
05/29/2008 | ENGINEERING - FINAL | Denied | COMPLETE ALL SITE WORK: NOT DONE-ALL ASPHALT PATCHES NEED TO BE COMPLETED PER COT STANDARDS CP-PATCH HOLES IN SOUTH PARKING LOT NOT DONE-ADDRESS CHANGE TO MAILBOX LOCATION ON SITE PLAN CP-REMOVE BOLTS AND CONDUIT FOR PAY TELEPHONE LOCATION OR PLACE PHONE PER PLAN CP-ENSURE ALL CONSTRUCTION TRAFFIC IS SEPARATED FROM PUBLIC ACCESS AREAS (N AND S SIDE OF BUILDING) NO ACCESS TO CURRENT MAILBOX LOCATION PARTIAL-REMOVE ALL CONSTRUCTION DEBRIS, MATERIALS AND TOOLS FROM PUBLIC AREAS -CLEAN UP NEW WASH OUT IN PARKING AREA (SOUTH SIDE) WEST OF MAILBOXES -PLEASE HAVE CHANGE TO MAILBOX LOCATIONS STAMPED PLAN SET AVAILABLE AT INSPECTION -REMOVE EXTRA PARKING STOP AT WEST SIDE OF PARKING LOT AND PLACE WHEEL STOP IN H/C SPOT -REMOVE ELECTRIC EXTENSION CORD FROM POOL AREA TO SECURITY TRAILER |
|
04/21/2008 | ENGINEERING - FINAL | Denied | COMPLETE ALL SITE WORK: -ALL ASPHALT PATCHES NEED TO BE COMPLETED PER COT STANDARDS -PATCH HOLES IN SOUTH PARKING LOT -ADDRESS CHANGE TO MAILBOX LOCATION ON SITE PLAN -REMOVE BOLTS AND CONDUIT FOR PAY TELEPHONE LOCATION OR PLACE PHONE PER PLAN -ENSURE ALL CONSTRUCTION TRAFFIC IS SEPARATED FROM PUBLIC ACCESS AREAS (N AND S SIDE OF BUILDING) NO ACCESS TO CURRENT MAILBOX LOCATION -REMOVE ALL CONSTRUCTION DEBRIS, MATERIALS AND TOOLS FROM PUBLIC AREAS |