Inspection History Details
Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T06CM04951
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/04/2008 | SITE - SEWER | Approved | IVRS - Inspection :* | |
05/14/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CLEAN OUT ALL DEBRIS FROM MANHOLES AUTHORIZATION TO DISCHARGE (PCDEQ) ON SITE |
|
05/12/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* TERMINATE ALL CLEANOUTS AND MANHOLE COVERS PROPERLY |
|
03/11/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. RETEST MANHOLE #6 2. VACUUM TEST OK 3. RICK ENG. PAPERWORK OK |
|
02/21/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #7 TO HCS AIR TEST OK MANHOLE #6 TO HCS OK MANHOLE #5 TO (2) HCS OK MANHOLE #4 TO HCS OK MANHOLE #3 TO (2) HCS OK |
|
02/20/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 6" SDR 35 FROM MANHOLE #7 SOUTH & WEST AIR TEST OK |
|
02/19/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 4" DIP FROM MANHOLE #6 TOWARD BLD. |
|
02/14/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
02/07/2008 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANDREL FROM PUBLIC #2 TO PRIVATE #1 TO PRIVATE MANHOLE #2 TO MANHOLE #1 TO #3 TO #4 TO #5 TO #6 TO #7 MANDREL OK AIR TEST PUBLIC MANHOLE #2 TO PRIVATE #1 OK AIR TEST PRIVATE MANHOLE #1 TO PRIVATE #2 OK AIR TEST PRIVATE #1 TO #3 OK AIR TEST PRIVATE #4 TO #5 OK AIR TEST PRIVATE #5 TO #6 OK AIR TEST PRIVATE #6 TO #7 OK |
|
02/04/2008 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* 1) CONTRACTOR CANCELLED |
|
12/28/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #7, 6" SDR 35 TO END OF LINE OK PENDING VERIFICATION OF GRADE & AIR TESTING |
|
12/18/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* VAC TEST MANHOLE #1, 2, 3, 4, 5 AND #7 OK VAC TEST MANHOLE #6 - NOT READY SHALL TEST MANHOLE #6 AT LATER DATE |
|
12/10/2007 | SITE - SEWER | Denied | IVRS - Inspection : See detailed listing on site.| 999* PIPING FROM MANHOLE #7 HAS BEEN INSTALLED AND COVERED WITHOUT INSPECTION, EXPOSE THIS PIPING FOR INSPECTION. |
|
12/05/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* EXCAVATION FOR 6" FROM MANHOLE #7 WEST |
|
12/04/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 4" HCS FOR BUILDING FROM MANHOLE #7 INSTALLED, TRACER WIRE, BEDDING, SHADING OK |
|
12/03/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR 35 CONTINUES WEST TO MANHOLE #7, WORKING ON HCS FROM MANHOLE #7, BACKFILLED TO MANHOLE #6 |
|
11/29/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* | |
11/28/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #6 BASE POURED, BACKFILLING CONTINUES |
|
11/27/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) BACKFILLING CONTINOUS MH #3 TO 4 TO 5 |
|
11/26/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* BACKFILLING CONTINUES |
|
11/21/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* BACKFILL AT MANHOLE 3-4, FROM MANHOLE #6 8" CONTINUES EAST 13', 4" HCS TO BLD, BEDDING, LAYING, TRACER |
|
11/20/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #3,4,5 BASES & STACKED FROM MANHOLE #5 TO MANHOLE #6 BEDDING, LAYING, TRACER, SHADING. HCS LATERALS FROM MANHOLE #4 & 5 |
|
11/16/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #5 84' TO THE WEST SDR 35 TRACER WIRE AND BEDDING OK |
|
11/15/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #4 & #5 BASES POURED PIPING FROM MANHOLE #4 & #5 OK 24' OF SDR35 FROM MANHOLE #5 ALL PIPING TO BE TESTED AT LATER DATE |
|
11/14/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CANCELLED |
|
11/13/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) PIPING SDR35 BEDDING FROM MAN HOLE #3TO MANHOLE #7 |
|
11/09/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 20' MOVE FEET OF SDR35 FROM MANHOLE #3 MORE THAN 11/8/07 |
|
11/08/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #3 104' TO WEST TO HCS A-1 PIPING, BEDDING AND TRACER WIRE OK |
|
11/06/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* - 50' WEST OF MANHOLE 3 BEDDING, LAYING, TRACER, SHADING OK - BASE OF MANHOLE #3 POURED |
|
11/05/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* FROM MANHOLE #1 TO MANHOLE #3 8" BEDDING, LAYING, TRACER, SHADE OK FROM MANHOLE #3 TO BLD. B 4" AND BLD. C-2 4" BEDDING, LAYING, TRACER, SHADING OK FROM MANHOLE 3, 13' WEST |
|
08/20/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) MANHOLE #2 POURED AND STACKED OK |
|
08/16/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* NO ONE ON SITE 2:55 PM |
|
08/10/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1) 8" SDR PIPING CONTINOUS TO MANHOLE #2, BONDING, LAYING, TRACER, ? OK |
|
07/19/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
07/16/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" SDR 35 CONTINUES SOUTH FROM MANHOLE #1 APP. 80' NORTH OF MANHOLE #2 BEDDING, LAYING, TRACER, SHADING OK |
|
07/12/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* CONTRACTOR CANCELLED |
|
07/11/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* | |
07/10/2007 | SITE - SEWER | Partial Approval | THIS INSPECTION FOR SITE SEWER PRE-CON MEETING ATTENDED BY RICHARD (DIVERSIFIED), MIKE & MATT (LAMB EXCAVATION), DEAN (RICK ENGINEERING) -- PROJECT TO BE INSTALLED PER PIMA COUNTY STANDARDS, INSPECTION DAILY DURING CONST. WITH AIR TESTING OF PIPING, VACUUM TESTING OF MANHOLES AT LATER DATE. AUTHORIZATION TO DISCHARGE FROM PCDEQ REQUIRED PRIOR TO HCS CONNECTIONS TO BUILDING. BEDDING, LAYING, TRACER WIRE FROM EXIST. MANHOLE #2 SOUTH APP. 200' OK |