Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/04/2008 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
04/11/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* WATER COOLERS INSTALL WATER PIPING PER PLAN ADD PLUMBING TO PLAYGROUND ACTIVITY |
|
02/26/2008 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* INSTALL 4" RPB PER APPROVED PLAN AND PROVIDE CORRECT TRANSITION FROM DUCTILE TO PVC SCH 40 PIPE |
|
02/14/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 2 1/2 SERVICE FROM METER INTO NORTH CENTER BLD A PRE-SCHOOL |
|
01/22/2008 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
07/11/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 8" SDR 35 FROM EXISTING MANHOLE #2 300' SOUTH BEDDING, LAYING, TRACER, SHADING OK |
|
07/10/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
07/06/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* UNDERGROUND WATER 10' FEET OF PIPE AND 90 DEG. OK |
|
07/05/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* CANCELLED |
|
07/03/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST BUILDING A CENTER & EAST P101A PER INITIAL ON SITE UNDERGROUND OK |
|
06/29/2007 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* WATER TEST UNDERGROUND FROM UPPER TERM C.O THRU BUILDING INITIALED ON PAGE P101.A OK PENDING LETTER FROM SMU GIVING OK FOR 3" DRAINAGE FOR BACK TO BACK STOOLS NOTE: SITE SEWER & WATER PLAN REQUIRES CITY OF TUCSON PLAN CHECK APPROVAL AND MAY REQUIRE PCDEQ APPROVAL YOU NEED TO ADD 03057 SITE SEWER & 03054 SITE SEWER PRE-CONSTRUCTION MEETING TO A PERMIT CARD OR HAVE A SEPARATE PERMIT CARD. THEN CALL IN AND HAVE THIRD PARTY INSPECTOR, CONTRACTOR, INSTALLER & CITY OF TUCSON INSPECTOR FOR 03054 PRE-CONST MEETING |