Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T06CM04763
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/30/2008 | BUILDING - PROGRESS | Approved | IVRS - Inspection :* | |
01/31/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection U-VALUE OK |
|
01/29/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* STUCCO LATHE OK EAST SIDE |
|
01/28/2008 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
01/25/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* UNDER CANOPY LATHE NORTH SIDE |
|
01/23/2008 | BUILDING - PROGRESS | Partial Approval | STUCCO MESH NORTH FACE OK |
|
01/15/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* BRACING ON PARAPET OK |
|
01/14/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* POUR BACK MECHANICAL ROOM, SHEETROCK NAILING |
|
01/08/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* ANGLE BRACING WELDING OK |
|
01/02/2008 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* FRAMING ON EAST PARAPET |
|
12/19/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* FRAMING ON PARAPET NORTH, EAST SIDES EXCLUDES CORNER |
|
12/17/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* FRAMING WEST HALF PARAPET, EXCLUDES WELDING |
|
12/04/2007 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
11/28/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* MECH. ROOM NAILING ON ROOF |
|
11/20/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* POUR BACKS OK |
|
11/15/2007 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* | |
11/06/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* WELDING GIRDERS NORTH POD |
|
11/05/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* WELDING ON GIRDERS SOUTHEAST POD |
|
11/01/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* WELDING OK |
|
10/08/2007 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* TILT PANELS OK |
|
10/05/2007 | BUILDING - PROGRESS | Not ready for Inspection | IVRS - Inspection :* |