Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T06CM04667

Parcel: 140552650

Inspection Status: Approved

Inspection History: BUILDING - FINAL

Date Description Inspector Results Comments
01/11/2007 BUILDING - FINAL Approved IVRS - Inspection :*
12/29/2006 BUILDING - FINAL Partial Approval IVRS - Inspection :*
1) YOU MUST PROVIDE CITY OF TUCSON APPROVED ENGINEERING REPAIR FOR THE 12" X 18" HOLE THAT WAS OUT IN THE POST TENSION FLOOR IN THE POWDER ROOM AND YOU MUST PROVIDE PROOF THAT A THIRD PARTY INSPECTION WAS MADE OF THE REPAIR. YOU MUST PROVIDE SPECIAL INSPECTION REPORT PROVING THAT THE REPAIR OF THIS SLAB WAS WITH MINIMUM 3000 PSI CONCRETE. YOUR ENGINEERING MUST STATE THAT HE ACCEPTS FULL RESPONSIBILITY FOR THE REPAIRED SLAB. THIS HOUSE WILL REMAIN ON TEMPORARY POWER UNTIL FINAL INSPECTION APPROVAL. CITY OF TUCSON RESERVES THE RIGHT TO DISCONNECT ELECTRIC POWER IF REPAIR IS NO ACCEPTABLE BY 01/29/07
12/27/2006 BUILDING - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) ITEMS 1, 3 & 4 OF 12/21/06 INSPECTION NOT DONE
2) INTERMEDIATE FRAME INSPECTION NOT APPROVED
3) SINCE THERE WAS NO CITY OF TUCSON INSPECTION OF THE 12 X 18" POST TENSION SLAB REPAIR. YOU MUST PROVIDE A SPECIAL INSPECTION REPORT VERIFING THE REPAIR WAS MADE WITH MINIMUM 3000 PSI CONCRETE. ONCE THE CONCRETE MEETS 3000 PSI STANDARDS THEN YOU MUST PROVIDE AN ENGINEERS AND CITY OF TUCSON APPROVED LETTER WHERE THE ENGINEER ACCEPTS THE REPAIR. THE LETTER DATED DEC. 8 2006 DOES NOT DO THAT
12/21/2006 BUILDING - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1. WH T&P LINE MUST EXHAUST DOWN
2. WATER LEAK GARAGE SEWER CLEANOUT
3. RANGE HOOD & OUTLET NOT IN
4. DISHWASHER DRAIN MUST LOOP TO 2" OF SINK FLOOD RIM
5. YOU MUST PROVIDE CITY OF TUCSON APPROVED ENGINEERING REPAIR FOR CUT POST-TENSION FLOOR
6. NO INSULATION CERT.