| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/18/2009 | ELECTRIC - UNDERGROUND | Approved | IVRS - Inspection :* | |
| 03/17/2008 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* OK TO CONTINUE WITH SITE ELECTRICAL TO POLE BASES GATE, INTERCOM AND DATA STAY MIN. 24" DEEP - NEC 300.5 - COVER AS NEEDED |
|
| 09/17/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* OK PVC CONDUITS UNDER SLAB WEST SIDE MAIN BUILDING |
|
| 09/06/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* STEVE PM 240-1345 MAIN BLDG - (3) 1" PVC'S TO ELEVATOR (1) 1 1/2 PVC TO PNL FEEDER EAST (6) 3/4" PVC'S BRANCH CIR'S |
|
| 08/29/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* OK 20' REBAR UFER, 3/0 COPPER ELECTRODE CONDUCTOR TO NEW BLD. |
|
| 08/23/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1. 30' 2" PVC SES TO TRANS T-1 2. 2 - 2" PVC's SES TO PNL H1A 3. 2 - 2" PVC's SES TO PNL H2B 4. 3 - 3/4" PVC OUT TO GATE MOTORS 5. 2 - 3/4" PARKING LTS & COMMUNICATION |
|
| 08/06/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1. (1) 2" CONDUIT FROM PNL M TO BOILER ROOM J-BOX 2. (2) 2" CONDUIT (SPARES) FROM PNL M LOCATION TO OUTSIDE SE CORNER BOILER ROOM & CAPPED 3. (2) 3/4" CONDUITS PNL M TO OUTSIDE SE CORNER BOILER BLD FOR CANOPY |
|
| 07/17/2007 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1. (6) 3" PVC'S SW GEAR TO TEP PAD 2. (4) 3" PVC'S SW GEAR TOWARD TEP PAD 3. (2) 4" PVC'S SW GEAR MID-SECTION TO 3RD SECTION 4. (5) 2" PVC'S SW GEAR OUT 10' TO NEW BLDG. DISCUSSED SERVICE CHANGE OVER AND SCHEDULING ON WEEKEND INSPECTION. DISCUSSED GROUNDING DETAILS POSSIBLE GFI ON SERVICE. |