| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/21/2007 | MECHANICAL - INTERMEDIATE | Approved | ||
| 04/27/2007 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. SECONDARY DRAINS MUST TERMINATE TO A CONSPICUOUS LOCATION. 307.2.3 2003 IMC 2. PVC NOT ALLOWED IN A PLENUM CEILING 602.2.1 3. PROVIDE MIN. 100 PSI HYDROSTATIC TEST OR HYDRONIC PIPING. 1208.1 4. OK PARTIAL CEILING TILES ROOM 25 |
|
| 04/17/2007 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. 1ST FLOOR ABOVE CEILING SIZE & SUPPORTS OK OK TO INSULATE 2. MEZZANINE EQUIP OK |
|
| 04/04/2007 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* ROOM 30 -- INSULATION OK OK TO START CEILING GRID |
|
| 03/20/2007 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* SUSPENDED ROUGH DUCT ROOM 30 OK TO INSULATE ALL DUCTS. |