Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Approval
Inspection History: ELECTRIC - INTERMEDIATE
Permit Number - T06CM04015
Inspection Description - ELECTRIC - INTERMEDIATE
Inspection Status - Partial Approval
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | OK CEILINGS ROOMS #19, 21, 28 I WILL CHECK DEMO, RACEWAY SEAL ABOVE PANELS AND REMAINDER LOW VOLTAGE AT LATER DATE |
|
05/01/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
04/27/2007 | ELECTRIC - INTERMEDIATE | Denied | 1. LIGHT FIXTURES OK 2. QUESTIONNABLE REACH ON CONDENSATE PUMPS INSTALL ONE PLUGGED. 3. POWER POLES NOT IN - LEAVE TILES OUT FOR INSPECTION 4. OK OTHER THAN #2 , #3 5. FINISH DATA & COMMUNICATION CABLE FOR INSPECTION 6. FINISH ALL WIRING IN CEILING - IF ASSOCIATED WITH FIRE ALARMS OR LOW VOLTAGE OCCUPANCY SENSOR. |
|
04/26/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | RMS 10, 11, 12, 22, 27 -- OK TO COVER | |
04/25/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
04/24/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
04/20/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | NOTES: 1. DATA/COMM LV CABLES NEED TO BE PLENUM RATED, INDIVIDUALLY SUPPORTED - SEE ART. 725 NEC 2. NEED TO INSP. TERMINATIONS INTO MODULAR FURNITURE FROM ABOVE CEILING ROOM #30 |
|
04/20/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled ROOM 30 CEILING TILES |
|
04/18/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
04/17/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | 1. OK WATER & BUILDING STEEL BONDING 2. BE ADVISED THAT DATA/COMM. CABLING WILL NEED TO BE PLENUM RATED & INDIVIDUALLY SUPPORTED IN A WORKMANSHIP LIKE MANNER PER 725 NEC |
|
04/16/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
04/04/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | VFD'S NEED 36" IN FRONT WORKING CLEARANCE | |
04/03/2007 | ELECTRIC - INTERMEDIATE | Cancelled | IVRS - AP canceled | |
03/26/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | OK 4" FEED BETWEEN MAIN 400A AT DSA TO PANEL SPHL OK TO TIE IN | |
03/23/2007 | ELECTRIC - INTERMEDIATE | Approved | IVRS - Inspection :* 1. TWO FIRST FLOOR BATHROOMS - CEILING OK 2. PANEL SPHC OK 3. TRANS T-3 OK TIGHTEN GROUND LUGS UNDER T-3 NUTS/LN'S 4. TIGHTEN 90 DEG. 4" FLEX ON FLEX SIDE 5. TRANS T-3 OK - ADD WATER BOND WHEN AVAILABLE 6. PNL LDP OK 7. PNL SPLC, SPLD, SPCE 8. WILL NEED TO SEE TERMINATIONS AT MAIN GEAR FOR POWER RELEASE |
|
03/13/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* ENTRY AREA OK |
|
03/12/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* RMS 17, 18, 19, 21, 1, 2, 3, 4, 5, 6, 7, 8, 13, 14 OK TO COVER |
|
02/22/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* OK WALL COVER BATHROOMS, AND ROOM #8, 9 WALLS |
|
02/14/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* OK WALLS ROOMS #10, 11, 12 |
|
02/05/2007 | ELECTRIC - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) ROOMS #011, 010, 030, 025, 019, 029 AND 018 WALLS OK 2) ALSO #2 GEC FOR TRANS ON MEZZ TO OUTSIDE 2 GROUND RODS AND GROUND RING (EXISTING) |