Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/21/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 12/19/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. SANITARY TEES ARE TO BE INSTALLED IN THE VERTICAL POSITION. 2. USE PROPER WYE PATTERN FITTING FOR GT VENT (TRY A WYE AND 1/6TH BEND) 3. CORRECT BACK PITCH ON GT VENT INSIDE BUILDING. 4. RETEST GT WASTE & VENT AFTER CORRECTING. 5. SANITARY DRAINAGE IS OK |
|
| 12/04/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. TEST TO BE IN PLACE ON ALL PIPING AT TIME OF INSPECTION. 2. YOUR FLOW CONTROL SHALL BE INSTALLED PER PLAN WITH CORRECT VENTING. ON GREASE WASTE IN TAILPIECE OF FIXTURE. 3. FLOW CONTROL TO BE SAME SIZE AS DRAINAGE (CANNOT PROVIDE 3" FLOW CONTROL ON 2" DRAIN PIPING). 4. PROVIDE LONG RADIUS DRAINAGE FITTINGS FOR VENT BELOW FLOOD RIM OF FIXTURE. SANITARY 2" DRAINAGE WATER TEST UNDERGROUND ONLY WITH PIPE WRAPS OK 5. CANNOT REVENT BELOW FLOOD RIM OF FIXTURE. 6. SHALL PROVIDE MINIMUM 2% FALL ON GREASE DRAINAGE. |
|
| 11/15/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :$ I WAS UNABLE TO LOCATE CONTRACTOR NEEDS TO POST ADDRESS CONTRACTOR MAY PROVIDE A CONTACT NUMBER. |