Permit: T06CM03904

Parcel: 119031360


Addresses:

750 W 41ST ST

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
10/13/2006 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :*
10/05/2006 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
PROVIDE FOAM PIPE WRAPS ON PIPING PENETRATING SLAB.
10/04/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
09/29/2006 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
- PLEASE READ NOTES FROM PREVIOUS INSPECTIONS.
- INSTALL FULL SIZE CLEANOUT ON SEWER, TEST.
- PROVIDE UNIFORM SLOPE ON 3" SEWER.
- CONNECT SEWER TO HCS AND CALL FOR INSPECTION.
- ADHESIVE TAPE IS NOT ALLOWED ON PEX, USE ZIP TIES.
- REMOVE ROCKS FROM AROUND PEX, SUPPORT PEX IN ALL AREAS.
- TEST, CALL FOR INSPECTION.
09/26/2006 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
ROUGH SOIL PIPING WITHIN BUILDING IS OK TO COVER.
09/25/2006 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
1. YOUR WATER TEST IS DOWN
2. YOUR TRANSITION COUPLING AT HCS CONNECTION IS UNDER STRESS, ASSURE PROPER ALIGNMENT.
3. PROVIDE A 4" CLEANOUT TO SERVE 4" SEWER.
4. TYPE L COPPER REQUIRED AT TRANSITION RISER.
5. JOINTS IN WATER PIPING SHALL BE UNDER TEST FOR INSPECTION.
6. CALL IN FOR INSPECTION; YARD WATER AND HCS, IF YOU WOULD LIKE TO HAVE THESE ITEMS INSPECTED.