Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2008 | ENGINEERING - FINAL | Approved | ||
| 05/19/2008 | ENGINEERING - FINAL | Denied | Contractor needs to: 1- Remove stockpile south side of project. 2- Stabilize area around stockpile. 3- Stabilize side slope next to trash enclosure. |
|
| 05/14/2008 | ENGINEERING - FINAL | Not ready for Inspection | Contractor needs to 1- Remove construction debris and material and re-veg all disturbed areas. 2- Stabilize slope next to driveway to trash enclosure. |
|
| 04/14/2008 | ENGINEERING - FINAL | Partial Approval | Contractor needs to complete items: 5- Build all basins per approved details. 7- Have all revisions to drawings approved at 201 North Stone. 11- Remove trash dumpsters from site. 15- Complete trash enclosure and provide access. 19- Clean all debris out of drainage channel south side of project. (trash, washout) |
|
| 03/10/2008 | ENGINEERING - FINAL | Partial Approval | OK for temp C of O with public access. Contractor still needs to complete final punch list and keep public access separated from construction activity and debris. | |
| 03/06/2008 | ENGINEERING - FINAL | Partial Approval | Contractor needs to complete items #1, 2, 14, 18 and 28 before public access. | |
| 03/04/2008 | ENGINEERING - FINAL | Partial Approval | Met on site with Tony site super. OK for temp C of O for staffing only. Contractor needs to complete items #1, 2, 14, 18, 21, 28 before full C of O issued. | |
| 03/04/2008 | ENGINEERING - FINAL | Partial Approval | PER JIM FEMLING OK TCO FOR STAFFING | |
| 02/25/2008 | ENGINEERING - FINAL | Denied | Contractor needs to complete: 1- Depress all landscape areas 6" max for water harvesting. Per note 29, sheet 1. 2- Provide letter from Engineer in regards to chapter XIV, section 14.2 (7) of the C.O.T. Drainage Manual. 3- Install all rip rap work per approved detail 6, sheet 5. Extend as needed to cover all erosion. 4- Clean silt out of all basins and water harvesting areas. 5- Build all basins per approved details. 6- Provide positive drainage for all basins. 7- Have all revisions to drawings approved at 201 North Stone. 8- Complete all work around Cabana and Pool. 9- Complete all hand rail work. 10- Remove port-a-pottys from site. 11- Remove trash dumpsters from site. 12- Remove all mini mobile units and trailers from site or obtain permits. 13- Stabilize all areas disturbed by construction. 14- Separate all construction activity and debris from public access. 15- Complete trash enclosure and provide access. 16- Complete 6' screen wall on east side of project. Per sheet 2. 17- Provide approved detail for all bleeder pipes. 18- Complete basin "B" discharge per approved details. Provide as-built elevation from discharge to scupper in right-a-way. 19- Clean all debris out of drainage channel south side of project. (trash, washout) 20- Install all weep holes in south side drainage per detail 7, sheet 4. 21- Complete hand rail around south side drainage channel. 22- Install sidewalk and scupper on south side of building per sheet 2. 23- Clean all wash out around site. Provide wash out area for sub-contractors. 24- Clean southeast corner of parking lot. 25- Complete sidewalk southeast side. 26- Install all bike parking per approved drawings. 27- Clean behind all scuppers, provide positive drainage. 28- Engineer needs to address basins holding water for longer then 24 hours. Wall opening to basins. 29- Address drainage across HC ramps front of building and parking areas on southwest corner of building. 30- Complete all HC signage. 31- Grout around bleeder pipe in basin "B". This is not a complete punch list Contractor will need to address items and call for re-inspection. |