Date Description Inspector Results Comments
07/02/2007 BUILDING PRE-SLAB Approved IVRS - Inspection :*
05/14/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1. THIS INSPECTION COVERS THE FOLLOWING AREA
EAST STAIR MECH. ROOM LAYOUT ON SHEET S10.2/2 SPECIFIC DETAIL ON SHEET S4.1/9 IN ACCORDANCE WITH APPROVED PLANS. PROVIDE RFI FOR 2 #5 DOWELS MISSED 8" O.C IN ACCORDANCE WITH DETAIL 1 ON SHEET S4.2
2. THIS INSPECTION COVERS THE FOLLOWING AREA,
EAST ELEVATOR CMU REINFORCING AT 8'-12' A.F.F.E
AND 17'-21' A.F.F.E -- OK TO GROUT.
05/11/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1) NOTE: THIS INSPECTION COVER THE FOLLOWING AREA EAST STAIR (MECH ROOM) IN COMPLIANCE WITH LAYOUT ON SHEET S10.2 AND SPECIFIC DETAIL ON SHEET S4.1/3
05/10/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1. NORTHWEST STAIR FOOTINGS AND SLAB IN COMPLIANCE WITH DETAIL 2 ON SHEET S10.3 AND DETAIL 1 ON SAME PAGE OR SHEET.
2. REINFORCED MASONRY PRE-GROUT INSPECTION COVER 12' A.F.F. OF OK TO GROUT
COMPLETE ELECTRICAL ROOM AND CALL FOR INSPECTION PRIOR TO GROUT.
05/09/2007 BUILDING PRE-SLAB Cancelled
05/01/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
THIS INSPECTION COVERS LEVEL 2 ON THE FOLLOWING
AREAS B.5-CO/1.0-11.0, D.0-D.5/1.0-11.0 IN COMPLIANCE WITH APPROVED PLANS AND SPECIFIC DETAILS
SPECIAL INSPECTION REPORT PROVIDED
04/30/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
LEVEL 2 GRIDLINES A.0-B.3/1.0-11.0
C.0-C.5/1.0-4.5 IN COMPLIANCE WITH APPROVED PLANS AND SPEC.
PLUS ELECTRICAL ROOM FOUNDATION IN COMPLIANCE WITH DETAIL 7 ON SHEET S4.1
SPECIAL INSP. REPORT PROVIDED
04/27/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
3RD FLOOR SLAB, SPECIFIC DETAIL ON SHEET S2.3
GRIDLINE D-E/1-11, E-F/2-10
3RD FLOOR SLAB C-D/8.5-11
LEVEL 2 TO 3 C.5/D.0/1.0-9 + C.5-D.0/9-11 OK
RAMP 2 TO 3 C-D/1-11
SPECIFIC DETAIL FOR ALL ABOVE IN COMPLIANCE WITH LAYOUT AND SPEC. ON SHEET S2.3
04/26/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
THIS INSPECTION COVERS 3RD FLOOR LEVEL REINFORCING ON SLAB.
GRIDLINES B.5-C.0/1.0-11
D-D.5/10-11
IN ACCORDANCE WITH APPROVED PLANS AND SPECIFIC DETAILS.
04/25/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1. 3RD LEVEL A-B.5 AND C-C.5
2. RAMP 2-3 C-C.5 OK
04/24/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
1. FINISH BULK HEAD
2. FINISH CHAIRING STEEL
3. INSTALL CORD STEEL AT CORNERS PER KEYNOTE B FOR SLAB REINFORCEMENT PP S2.2
4. CORD STEEL PER KEYNOTE A - PP S2.2 AND 2 #4 PER DETAIL
5. PLEASE HAVE ALL STEEL WORK READY AT LEAST ONE DAY AHEAD OF YOUR POUR SCHEDULE
04/23/2007 BUILDING PRE-SLAB Partial Approval IVRS - Inspection :*
PROGRESS MEETING FOR PARKING FLOOR TOPPER POUR AT ALL FLOORS TO BEGIN THUR. 4/26/07 @ 2 AM
RECALL FOR TOMORROW & WED