Permit: T06CM03541

Parcel: 141153550

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
06/01/2007 ENGINEERING - FINAL Approved ALL ISSUES HAVE BEEN ADDRESSED
02/13/2007 ENGINEERING - FINAL Partial Approval TEMP C OF O APPRVD 12/30/05 BY DROBERTS

NO PERM C OF O UNTIL WHOLE SITE IS COMPLETE

DRAINAGE AT SE SIDE OF BUILDING IS BEING CHANGED
12/06/2006 ENGINEERING - FINAL Partial Approval REINSPECT FOR TEMP C OF O EXTENSION
NO FURTHER WORK HAS BEEN DONE
11/09/2006 ENGINEERING - FINAL Partial Approval APPROVED FOR TEMP C OF O ONLY
PER PAUL MACHADO AND PATRICIA GEHLEN
REVISED DEVELOPMENT PLAN AND REVISED GRADING PLAN MUST BE RECEIVED BEFORE THIS PAD CAN BE RELEASED TO FULL C OF O

SEE 11/7 COMMENTS
11/08/2006 ENGINEERING - FINAL Not ready for Inspection PICTURE FROM 11/07 ADDED
11/07/2006 ENGINEERING - FINAL Not ready for Inspection PER MTG DOWNTOWN WITH PATRICIA GEHLEN, PAUL MACHADO, DAVE SIROTA: A NEW DEVELOPMENT PLAN WILL BE NEEDED FOR SITE, A NEW GRADING PLAN SHOWING CHANGES TO DRAINAGE SOUTH OF PAD 4
THIS TI CAN BE ISSUED A TEMP C OF O ONLY
10/24/2006 ENGINEERING - FINAL Not ready for Inspection TALKED TO BILL POTTER REGARDING C OF O
RESEARCH ON PERMIT T05CM00616 PULLED BY RIO WEST FOR SUITE 112. THIS TI ENCOMPASSES BOTH SUITE 118 AND 112. EMAIL TO BETH GRANT.
09/05/2006 ENGINEERING - FINAL Not ready for Inspection JADE CONCRETE WASHING OUT TO EAST OF THE BUILDING
CALLED BILL POTTER WITH FINA AND ADVISED THAT ALL MUST BE CLEANED UP
08/30/2006 ENGINEERING - FINAL Not ready for Inspection TALKED TO BILL POTTER WITH FINA
LEFT MESSAGE FOR BILL HUFF WITH FINA
WORK NOT STARTED YET-FRAZEE PAINT
MADE BILL POTTER AWARE THAT TEMP C OF O ONLY UNTIL SHELL IS FINALED/SITE WORK COMPLETE