Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/12/2007 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 02/08/2007 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1) TEST AND EXPOSE ROOF DRAINS FOR INSPECTION 2) INSTALL EXPANSION JOINTS AT PLASTIC DRAINS 3) PROVIDE ACCESS TO ROOF |
|
| 10/13/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* PIPE WRAPS OK FOR CONCRETE |
|
| 09/08/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* - OK TO COVER ROUGH PLUMBING - RECALL ROUGH INSPECTION PRIOR TO CONCRETE FOR PIPE WRAP INSPECTION AND FS INSTALLATION. - FIXTURE FITTINGS INSTALLED PER RED LINES ON SHELL PLAN. - BUILDING SEWER CONNECTED TO PVC STUB AT 2 WAY CO - CALL FOR ROUGH PLUMBING AND HCS WHEN APPROVED TI PLAN BECOMES AVAILABLE. |
|
| 09/07/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* - WATER TEST NOT TO TOP OF RISER - GROUND WET FROM RAIN, UNABLE TO BE SURE THAT NO LEAKS EXIST. - ALSO MUD HAS COVERED MOST OF THE PIPING, UNABLE TO CHECK FALL. - SUPPORT WC TRAP ARM - SHELL PLANS DO NOT SHOW FIXTURES TO BE INSTALLED, REDLINE PLANS. |