Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/12/2007 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 10/23/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | ||
| 10/20/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO GROUT |
|
| 10/17/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) WEST WALL-NORTH APPROVED AT 14' AND BOND BEAM 2) TOP OUT REMAINING WALLS AND INSTALL BOND BEAM-RECALL PRIOR TO GROUT |
|
| 10/13/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) WEST WALL-NORTH 25-12' LIFT OK 2) EAST WALL 8' LIFT OK 3) WEST WALL SOUTH 30'-8' LIFT OK |
|
| 10/06/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST 48" LIFT EAST AND WEST WALLS 2) 8' LIFT SOUTH WALL CARPORT 3) PORCHES NOT READY |
|
| 08/25/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) OK TO CONTINUE |