Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T06CM03210
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/31/2007 | ENGINEERING - FINAL | Approved | ||
10/26/2006 | ENGINEERING - FINAL | Partial Approval | OK FOR TEMPORARY C OF O 1. COMPLETE ALL SITE WORK AS SHOWN ON THE PLAN. 2. FINE GRADE RETENTION/DETENTION BASINS. 3. PROVIDE A LETTER FROM THE ARIZONA REGISTERED P.E. THAT CERTIFIES THAT THE PROJECT WAS CONSTRUCTED IN CONFORMANCE WITH THE APPROVED PLANS AND WILL FUNCTION AS DESIGNED. 4. PROVIDE (1) MORE PARKING SPACE. 5. PROVIDE (6) CLASS I BICYCLE PARKING SPACES. 6. CLEAN OUT AND REMOVE DEBRIS FROM CATCH BASINS AND STORMDRAINAGE SYSTEM, EAST OF BUILDINGS. 7. ADDRESS RAINWATER LEADERS DISCHARGING TO SIDEWALK ON EASTSIDE OF BUILDING, PROVIDE SIDEWALK SCUPPERS. |
|
10/12/2006 | ENGINEERING - FINAL | Denied | 1. PROVIDE PLANS AND PERMIT CARD FOR INSPECTION. 2. PROVIDE ENGINEER'S CERTIFICATION THAT THE SITE WORK HAS BEEN CONSTRUCTED TO THE C.O.T. APPROVED PLANS. 3. CERTIFICATE OF OCCUPANCY NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR T05BU02237 IS COMPLETED AND APPROVED. |