Inspection Status: Approved
Inspection History: PLUMBING - MEDICAL GAS/TEST
Permit Number - T06CM03198
Inspection Description - PLUMBING - MEDICAL GAS/TEST
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2006 | PLUMBING - MEDICAL GAS/TEST | Approved | IVRS - Inspection :* - ALL PIPING INSTALLED AND UNDER 150 PSI TEST - LABELS OK - CALL FOR FINAL AFTER RECEIVING FINAL APPROVAL FROM CACTUS MEDICAL. |
|
09/13/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* 2 INSTALLERS WORKING LINES STUBBED INTO RM FOR TIE IN LABELS BEING INSTALLED |
|
09/12/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | BELOW FLOOR ISOLATION VALVES BEING INSTALLED BE SURE TO SUPPORT BEFORE BRAZING TO ENSURE COMPLETE MAKE UP OF FITTINGS. | |
09/11/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | MED GAS PIPING CONTINUATION IN LOWER LEVEL LOG BOOK OK 2 INSTALLERS WORKING |
|
09/01/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* GROUND FLOOR OK TO COVER |
|
08/31/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* | |
08/30/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* 150 PSI TEST ON ENTIRE SYSTEM DOWN STREAM OF ZONE VALVES. MA, MV, 02 |
|
08/29/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* TWO INSTALLERS WORKING BLOW DOWN PERFORMED, ALL OUTLET BOXES TIED INTO PAPERWORK UP TO DATE |
|
08/28/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* MED GAS PROGRESS CONTINUING 2 INSTALLERS WORKING. |
|
08/24/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* PAPERWORK CHECKED 2 INSTALLERS ON OVERHEAD PIPING |
|
08/23/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* WESTEND OUTLET BOXES TIED IN PROGRESS ON OVERHEAD PIPING ULTRA HIGH PURITY NITROGEN BEING USED ON ALL 3 SYSTEMS. |
|
08/22/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* PROGRESS CONTINUING. BLOW DOWN ON WEST END INSTALLING OUTLET BOXES ALARM PANEL MOUNTED. |
|
08/21/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* | |
08/18/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* | |
08/17/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* DAILY LOG CHECKED PIPING MOSTLY COMPLETE IN WEST END PATIENT ROOMS. |
|
08/16/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* DAILY LOG BEING KEPT ON NOTE PAD, CONTRACTOR WILL OBTAIN PROPER FORMS FROM CACTUS MEDICAL OUTLET BOXES BEING INSTALLED, OVERHEAD O(2) AND MA W/PARTIAL TEST ON PIPING INSTALLED. CALL FOR DAILY INSPECTIONS. |
|
08/14/2006 | PLUMBING - MEDICAL GAS/TEST | Not ready for Inspection | NO PAPERWORK ON SITE CALL FOR MASONRY INSPECTION |
|
08/10/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* 2" MV, 1" MA AND 1" 02 VALVE BOX INSTALLED & PIPED, PIPING OVERHEAD IN PROGRESS. HAVE PAPERWORK ON SITE. ISOLATION STUDS AND SAFETY PLATES NOT YET IN PLACE. |
|
08/08/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* CAPPED PIPING ON RACK, TYPE K COPPER BRAZING HAS NOT STARTED DO CALL IN FOR DAILY INSPECTIONS IF PROGRESS IS BEING MADE. |
|
08/07/2006 | PLUMBING - MEDICAL GAS/TEST | Partial Approval | IVRS - Inspection :* JIM SAMULSON 940-2056 HANGERS INSTALLED MATERIAL STORAGE IN GANG BOX CAPPED PIPING ON SITE. PROTECTED FROM DAMAGE UHP NITROGEN, ALARMED REGULATOR AND OXYGEN SENSOR ON SITE. |