Permit: T06CM03031

Parcel: 12510003F


Addresses:

3413 E BROADWAY BL

Inspection Status: Approved

Inspection History: REINFORCED MASONRY PRE-GROUT

Date Description Inspector Results Comments
07/18/2007 REINFORCED MASONRY PRE-GROUT Approved IVRS - Inspection :*
ALL EXTERIOR WALLS ARE TOPPED OUT AS PER ELEVATION PLANS -- OK TO GROUT & CAP
LINE A/3 TO A.75/5
07/17/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH WALL - A/3 TO A/4.75; NE & E WALL 4/4.75 TO B/5 @ 24'
OK TO GROUT
07/16/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTHWALL @ 20'; LINE A/3 TO A/4.5, NE CORNER @ 20'
LINE A/4.5 TO A-8/5 OK TO GROUT
07/13/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
LINE A/3 TO B/5 @ 54" ABOVE BEAM
OK TO GROUT & SET EMBEDS
07/05/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
SE WALLS LINES D.5/5 - D.5/5.5; D.5/5.5 TO E/6
NE POPOUTS - TOPPED OUT -- OK TO GROUT PROGRESS AREAS
07/03/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
SOUTH WALL @ 27' LINE E/2 - E/3;
NORTH & NW POP-OUTS @ 20'
OK TO GROUT PROGRESS AREAS
07/02/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
2 @ PIERS @ 11'4", A/4.7 TO A.5/5;
EAST WALL @ 24'8" LINE A/5 TO D.5/5
D.5/5 TO D.5/6 @ 24'8", D.5/6 TO E/6, E/6 TO E/1 @ 24'8"
SW POPOUTS @ 20' --- OK TO GROUT PROGRESS AREAS
06/29/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST WALL B.5/1 TO C.5/1 2 20'8"
POPOUTS A/1.2 TO A/3' D.5/1 TO E/1.2 @ 16' -- OK TO GROUT
06/28/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST WALL A/5 TO E/6 @ 20'8"
SOUTH WALL E/1 TO E/6
WEST WALL D/1 TO E/1;
B.25/1 TO A/1.2 @ 20'8"
POPOUTS @ 12'; C/1 & C.5/1 @ 16'
OK TO GROUT PROGRESS AREAS
06/27/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
2 @ PIERS @ A/4.8 AND A.25/5 - 8' - OK TO GROUT
POPOUTS ON NORTH, WEST & SOUTH WALLS (3RD LIFT) OK TO GROUT
06/26/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
LINE A/5 TO D.5/5; D.5/5 TO D/6; D/6 TO E/6; E/6 TO E/4.5
LINE C/1 TO A/1; A/1 TO A/3 @ 16'8" OK TO GROUT
06/25/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
LINE E/1 TO E/5 @ 12'8 TO 16'8;
LINE D/5 TO D/6; D/6 TO E/5 @ 12'8" -- OK TO GROUT
06/22/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
NORTH WALL @ 12' LINE A/1 TO A/3;
WEST WALL @ 12' LINE A/1 TO E/1
SOUTH WALL @ 12' LINE E/1 TO E/5
EAST WALL @ 12' LINE A/5 TO E/5
ALL POPOUTS @ 2ND LIFT OK TO GROUT
06/21/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
LINES E/1 TO E/6 @ 12'; B.5/1 TO E/1 @ 12'
POPOUTS A/1 TO A/3 @ 4'8"; B.5/1 TO E/1; E/1 TO E/1.2
WALL: A/1 TO P 1/3 @ 8' -- OK TO GROUT
06/20/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
A/1.2 TO A/3 @ 4'
A/5 TO E/6 @ 8'
E/1 TO E/6 @ 8'
A/1 TO E/1 @ @ 8'
OK TO GROUT
06/19/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
FIRST LIFT 2 4'
LINES E/6 TO E/1; TO A/1 OK TO GROUT
06/12/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST LOADING DOCK WALL - TOPPED OUT @ 10'
BOND BEAM W/2 @ #4'S -- OK TO GROUT
06/11/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
EAST LOADING DOCK WALL @ 4'8" -- OK TO GROUT
06/07/2007 REINFORCED MASONRY PRE-GROUT Partial Approval IVRS - Inspection :*
CONTINUOUS FOOTINGS @ 24" - COLUMN FOOTINGS @ 24"
LOADING DOCK AREA - BOND BEAM @ 16" - REBAR @ 8" O.C
FOOTING @ 64" OK TO POUR