Permit: T06CM02902

Parcel: 115150290


Addresses:

2115 N ORACLE RD 01


Inspection Status: Partial Approval

Inspection History: PLUMBING - INTERMEDIATE

Permit Number - T06CM02902

Inspection Description - PLUMBING - INTERMEDIATE

Inspection Status - Partial Approval

Date Description Inspector Results Comments
07/10/2006 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1. COPPER PASSING THRU MASONRY TO BE PROTECTED
2. REQUIRE 18" OF COPPER BEFORE TRANSITION TO PEX AT WH.
07/10/2006 PLUMBING - INTERMEDIATE Approved IVRS - Inspection :*
CORRECTIONS MADE OK
OK TO COVER ALL AREAS
07/05/2006 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1. PRESSURE BALANCE VALVES ON T&S COMBOS OK
2. PLUMBER WORKING ON CORRECTIONS.
07/03/2006 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1. NO UNDERGROUND INCLUDED ON THIS PERMIT.
WORK BEGAN AT INTERMEDIATE STAGE.
2. SEE NOTE #2 ABOVE. NO EXCEPTIONS!
VALVES IWTH INTEGRAL STOPS ARE VALVES THAT HAVE SHUT OFFS FOR HOT & COLD BUILT INTO THE VALVE.
06/30/2006 PLUMBING - INTERMEDIATE Partial Approval IVRS - Inspection :*
1) PLAN CALLS FOR PRESSURE BALANCE WITH INDIVIDUAL CONTROL T & S VALVE
2) SECURE CLOSET FLANGES TO FLOOR
3) HORIZONTAL X HORIZONTAL CHANGE OF DIRECTION TO BE A SWEEP (TRAP ARM)
4) TRAP ARM MAY NOT CHANGE SIZE AND TRAP AND TRAP ARM TO BE SAME SIZE
5) ABS IS TO BE SUPPORTED AT EACH CHANGE OF DIRECTION OR ELEVATION AND AT THE END OF BRANCHES THEN NO MORE THAN FOUR FEET BETWEEN HANGERS
6) THROUGHLY CLEAN AND REMOVE ALL RECTOR SEAL #5 FROM ABS THROUGHLY
7) WATER TEST ON ABS OK
06/26/2006 PLUMBING - INTERMEDIATE Not ready for Inspection IVRS - Inspection :*
1) ABS DWV UNDERGROUND INSTALLED AND COVERED WITHOUT INSPECTION. I WILL NOT APPROVE INTERMEDIATE UNTIL ROUGH SOIL IS APPROVED
2) NOTE: ABS TO BE SUPPORTED AT EACH CHANGE OF DIRECTION OR ELEVATION AND AT THE END OF BRANCHES
3) T & S VALVE-NEEDS INTEGRAL STOPS
4) SUPPORT COPPER AS REQUIRED