Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2007 | ENGINEERING - FINAL | Approved | All items on punch list approved. | |
| 03/09/2007 | ENGINEERING - FINAL | Partial Approval | Contractor needs to: 1- Complete gate. 2- Install dumpster pad, per note 8. 3- Complete striping, per note 17. 4- Backfill south side of block screen wall. 5- Install sidewalk, per note 14. 6- Install post barricade. 7- Remove all debris from HC parking area. 8- Install protection for bleeder pipe. Spoke to Terry site super. |