Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2007 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 02/09/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* SITE WALL SOUTHSIDE -- FINISH SETTING VERTICALS OK TO POUR FOOTING |
|
| 02/02/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) 2 LIGHT POLE BASE EAST END |
|
| 01/16/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 6 LIGHT POLE BASES SOUTHSIDE OF PROPERTY |
|
| 01/11/2007 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999* NO SUPERINTENDENT ON JOB SITE TO PROVIDE APPROVED PLANS AND IRC REGARDING INSPECTION TO COVER |
|
| 01/08/2007 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 5 LIGHT POLE BASES |
|
| 12/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 2 LIGHT POLE BASE SOUTHSIDE, FUEL TANK PAD |
|
| 12/20/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 3 LIGHT POLE BASES EAST END |
|
| 12/15/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 14 LIGHT POLE BASES |
|
| 12/13/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 8' WALL BETWEEN SALES AND CARWASH |
|
| 12/12/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 12/08/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 8' WALL BETWEEN CARWASH AND SALES |
|
| 11/15/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* NORTH DELTA GATE FOOTING |
|
| 11/14/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 7 LIGHT POLE BASE, 2 PATH FOOTING WEST END. |
|
| 10/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LIGHT POLE BASE NORTH SIDE |
|
| 10/19/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 10/16/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 9 LIGHT POLE BASES ON NORTHSIDE WEST TO EAST |
|
| 09/27/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COLUMNS ON NORTHSIDE OK |
|
| 09/21/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 09/14/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* INTERIOR FOOTINGS OK |
|
| 09/13/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* INTERIOR COLUMNS AND NORTHWEST CORNER |
|
| 08/30/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LINES G/F 15-9 I 15-18-0 |
|
| 08/29/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 08/28/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* G16 - Q.1 - Q-G |
|
| 08/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* INCOMPLETE |
|
| 08/24/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GRIDLINE G-C, E-6, 4-16 |