Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2006 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* 1) TWO LENTALS AT CMU OPENING AS PER PLANS 2) NOTE: MUST GET INSPECTION 03052 PLUMBING GAS PRESSURE TEST FINAL ADDED TO PERMIT |
|
| 10/10/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* TUNNEL CAP OK TO POUR |
|
| 10/04/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REBAR @ PIT WALLS -- OK TO POUR |
|
| 09/28/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WITNESSED EPOXY DOWELING OF 51 DOWELS @ SLAB |
|
| 09/26/2006 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PIT FLOOR REBAR OK TO POUR |
|
| 09/07/2006 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* RAIN FLOODED EXCAVATION |