Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2008 | ENGINEERING - FINAL | Approved | ||
| 05/23/2008 | ENGINEERING - FINAL | Partial Approval | SITE WORK IS GETTING CLOSER TO BEING COMPLETE RIP RAP WORK STILL NEEDS TO BE DONE ON EAST SLOPE |
|
| 05/22/2008 | ENGINEERING - FINAL | Partial Approval | THE SITE WAS CHECKED TO VERIFY WHAT WORK HAS BEEN COMPLETED FROM THE PREVIOUS LIST. 1) THE CONTRACTOR HAS INSTALLED THE TRUNCATED DOMES ON THE WHEEL CHAIR ACCESS RAMP. 2) THEY HAVE PERFORMED SOME GENERAL CLEAN-UP OF THE SITE, BUT STILL HAVE CONSTRUCTION MATERIAL THAT NEEDS TO BE REMOVED FROM THE LOADING ZONE LOCATED ON THE NORTH SIDE OF THE BUILDING. THE ITEMS STILL REMAINING TO BE COMPLETED AT THIS TIME IS THE PLACEMENT OF THE ROCK RIPRAP ALONG THE EAST SIDE OF THE SITE ADJACENT TO THE LA MIRAPOSA SITE. THIS WORK WILL BE COMPLETED SOMETIME NEXT WEEK IF POSSIBLE AT WHICH TIME A RE-INSPECTION WILL BE SCHEDULED TO CLOSE OUT ALL REMAINING OPEN PERMITS. | |
| 05/21/2008 | ENGINEERING - FINAL | Cancelled | CANCELLED PER CONTRACTOR | |
| 05/16/2008 | ENGINEERING - FINAL | Not ready for Inspection | -PLACE TRUNCATED DOMES AT BOTTOM OF H/C RAMP -PLACE RIP RAP (ON FILTER FABRIC) AND CONCRETE RIP RAP AT OUTFALLS OF PARKING LOT -GENERAL CLEAN UP |