Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2006 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 07/24/2006 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :* | |
| 07/21/2006 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 1ST LIFT APPROVED |
|
| 07/20/2006 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) REINFORCED CELLS MUST BE FILLED WITH GROUT-DON'T FILL CELLS WITH MORTAR 2) REBAR REQUIRED IN ALL FOUR CELLS OF COLUMNS 3) REBAR MUST LAP MINIMUM 24" |