Inspection Status: Approved
Inspection History: SITE - SEWER
Permit Number - T06CM01872
Inspection Description - SITE - SEWER
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2007 | SITE - SEWER | Approved | IVRS - Inspection :* BLD A 2-WAY CLEANOUT & HCS OK TERMINATE TRACER WIRE |
|
10/24/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* - MANHOLE FROM MANHOLE #1 TO EXISTING OK - 6" FROM MANHOLE #2 TO 1' FROM BUILDING SEWER AIR TEST OK 1. SHALL SEE CORRECT TIE IN AT THIS POINT AIR TEST MANHOLE #3 TO EXISTING OK AIR TESTING THIS PROJECT OK MANDREL OK MANHOLE VACUUM TESTING OK 1. NEED 2-WAY CLEANOUT AT BLD. A BUILDING DRAIN TO SEWER CONNECTION WITH INSPECTION. NEED CITY APPROVED REVISED PLAN WITH VERIFICATION OF GRADES TO FINAL. 2. NEED TO SEE CONNECTION AT TEMPORARY - EJECTOR PUMP LOCATION |
|
10/23/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MANHOLE #1 VACUUM TEST OK MANHOLE #2 VACUUM TEST OK MANHOLE #3 VACUUM TEST OK MANHOLE #1 TO #2 AIR TEST OK MANHOLE #2 TO #3 AIR TEST OK MANHOLE #2 TO HCS 6" NOT READY HALL TEST MANHOLE #3 TO EXISTING MANDREL MANHOLE #1 TO #2 TO #3 OK |
|
10/22/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* VACUUM TEST TO HOLD MINIMUM TIME WITH 1" LOSS MAXIMUM |
|
10/18/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8" TIE IN FROM SOUTHEAST BUILDING LOCATION TO STUB FROM MANHOLE OK |
|
10/17/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* PROVIDE APPROVED COUPLINGS FOR SEWER CONNECTION |
|
10/16/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* MH 3 BASE OK. ALL PIPING HAS BEEN INSTALLED. STILL NEED TO WITNESS TESTING. STILL NEED APPROVED PLAN REVISIONS AND VERIFICATION OF GRADE. |
|
10/15/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* PIPING FROM MH2 TO BUILDING OK, PIPING FROM MH3 TO BUILDING OK WILL INSPECT TIE IN AFTER SEWER IS COMPLETE PIPING FROM MH2 TO MH3 OK BASE NOT POURED INSTALL WATER STOPS |
|
10/10/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* DO NOT CONNECT TO BUILDING UNTIL SEWER AND MH TESTING IS COMPLETE |
|
09/24/2007 | SITE - SEWER | Not ready for Inspection | IVRS - Inspection :* MH #2 WILL INSPECT MH INTERIOR AT TIME OF TEST |
|
09/18/2007 | SITE - SEWER | Denied | IVRS - Inspection : See detailed listing on site.| 999* MH #2 BASE COVERED COORDINATE INSP. TO REMOVE LID FOR VISUAL INSP OF BASE INTERIOR |
|
09/12/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 8' SEWER CONTINUATION TO 40' PAST 6" WATER MAIN D1 INSTALLED 2' ABV WATER MAIN INSTALL TRACER WIRE BEFORE COVERING |
|
07/19/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 28' OF SEWER CONTINUED FROM LAST INSP. SPLICE TO TRACER WIRE W/WEATHER RESISTANT WIRE NUT |
|
04/20/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 130' INSTALLED S. OF MANHOLE #1 CALL FOR INSPECTIONS AS SOON AS PROGRESS IS CONTINUED PROVIDE DETAIL 208 |
|
04/19/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* 1. PIPING BEING INSTALLED PER DELTA 6 REV ON UNAPPROVED CIVIL DRAWING. 2. MANHOLE #1 AND PIPING INSTALLED W/OUT INSP. 3. CALL FOR DAILY PROGRESS INSPECTIONS PRIOR TO COVERING. 4. PROVIDE WWM DETAIL 208 |
|
04/19/2007 | SITE - SEWER | Partial Approval | FROM MANHOLE #1, APPROX 100' INSTALLED OK TO COVER, FINAL APPROVAL REQUIRES TESTING AND VERIFICATION OF GRADE. CONTINUE TO CALL FOR INSPECTIONS. |
|
01/18/2007 | SITE - SEWER | Partial Approval | IVRS - Inspection :* GARY 488-6274 BFL AND MIKE LAMB EXCAVATION 631-6433 1. SITE SEWER BEING INSTALLED PER DELTA REVISION #5 9/06 2. CITY APPROVAL OF REVISED PLAN REQUIRED. 3. ONE SECTION OF 8" SDR LAYED AND CONNECTED TO EXISTING MANHOLE #1 4. WATER STOP INSTALLED. 5. PLASTIC PIPING REQUIRES A GRN TRACER WIRE ATTACHED TO PIPE. 6. TEST ON PIPING REQUIRED. 7. THIS CAN BE DONE LATER. 8. CALL FOR DAILY PROGRESS INSPECTIONS 9. INSPECTIO OF MANHOLE BASES REQUIRED AND VACUUM TESTING OF NEW MANHOLE REQUIRED. 10. PROVIDE VERIFICATION OF GRADE OF PIPING. |