Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2006 | PLUMBING - ROUGH, SOIL | Approved | ||
| 04/10/2006 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* NOT UNDER TEST PLAN SHOWS 4" EXISTING @ 3" IS PRESENT. REDLINE PLAN TO SHOW 3" WASTE AND 3" FCO. PLANS CALLS FOR 2" TO P-4. 3" IS INSTALLED REDLINE CHANGE PROVIDE A 3" CLEANOUT AT UPPER TERMINAL. PLASTIC THREADS CANNOT BE CONCEALED, USE TEST TEE W/PERM CAP. HORIZONTAL CHANGES OF DIRECTION REQUIRE LONG RADIUS FITTINGS. USE SWEEP AT URINAL OR ELIMINATE 90 DEGREE. VENT TERMINATION ABOVE PARAPET TRAP PRIMER UNION SOLDERED SHUT WIPE SOLDER JOINTS SECURE DROP EAR EII AT MOP SINK. PROVIDE PIPE WRAP WHERE PENETRATING SLAB. |
|
| 04/07/2006 | PLUMBING - ROUGH, SOIL | Cancelled | CANCELLED PER SUPERINTENDENT ADAM #272-0471 | |
| 04/07/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* |