Permit: T06CM01331
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/02/2006 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* CORRECTIONS MADE OK OK TO COVER ALL AREAS |
|
| 11/01/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 10/30/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 10/26/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* | |
| 10/25/2006 | PLUMBING - INTERMEDIATE | Cancelled | IVRS - RI canceled | |
| 10/23/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* ABS TO BE SUPPORTED AT EACH CHANGE OF DIRECTION OR ELEVATION AND AT THE END OF BRANCHES, THEN NO MORE THAN FOUR FEET BETWEEN HANGERS. USE APPROVED STRAPS REQUIRE 18" OF COPPER AT SERVICE AND WATER HEATER SUPPORT TRAP ARMS HORIZ X HORIZ CHANGE OF DIRECTION TO BE A SWEEP |
|
| 04/20/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. ABS MAY NOT BE RUN IN THE FOOTING 2. CORRECT BACKPITCHED SECTION. |
|
| 04/19/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* UPPER FLOOR ROUGH PLUMBING OK |
|
| 04/17/2006 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1. OWNER TOOK OPTION FOR DOWNSTAIRS BATHROOM. NO APPROVED PLAN ON SITE. INSTALLED PER REDLINES. LOCATION OF UPSTREAM MANHOLE MANDATES A "DUAL" ROUGH IN LOWER ROUTH INSTALLED PER REDLINES OK TO COVER SUBJECT TO REVISED APPROVED PLAN OK TO PLACE 2ND FLOOR PLUMBING AND RECALL FOR INSPECTION. |
|
| 04/14/2006 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* 1. NO APPROVED PLAN SITE PLAN APPROVED IN ERROR (140 BACKWATER VALVES) 2. PLUMBER PROVIDED 8 1/2" x 11" "AS BUILT" PLUMBER DIDN'T PROVIDE WRITTEN ELEVATIONS OF FLOOR LEVEL AND OVERFLOW OF UPSTREAM MANHOLE. 3. PLUMBER TO LAY LOWER ROUGH ON A FIRM BED, SHADE THE PIPE AND HAVE IT INSPECTED, THAN THE PLUMBER WILL LAY THE UPPER ROUGH ON A FIRM BED, SHADE THE PIPE AND CALL IT IN FOR INSPECTION. |