| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/25/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 08/08/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/03/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/02/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* CHECK #25274 ALL CLEANOUT FLOOR AND WALL ARE INSTALLED IN DELI OK TO COVER |
|
| 08/01/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* CHECK #2547 DELI FLOOR SINKS PER RED LINE DRAWING |
|
| 07/25/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | MEAT DEP. HAND SINK UNDERGROUND OK | |
| 07/24/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SPECIAL INSPECTION PAID W/MONEY ORDER 5558428530 FLOOR SINK AT ENTRANCE (COL. D.8/6) OK. INSTALL CLEAN OUT. OK TO COVER AFTER INSTALLING, PROVIDE WATER TEST ON VENT THRU ROOF. WASTE FOR DF INSTALLED PER REDLINES AT SAME LOCATION OK - PROVIDE TEST ON VENT WATER PIPING IS OK. BEV. DISPENSER HAS CARBONATED, NON-CARBONATED WATER AND ICE MAKER. 3 BACKFLOW PREVENTORS WILL BE REQUIRED ONE FOR EACH CONNECTION. |
|
| 07/19/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HRS. INSP. CHECK #5533726445 WATER TEST CONTINUATION OF 4" GREASE WASTE FROM 6/30/06 INSPECTION P1.2 TO 5/25/06 INSPECTION P1.2 4' MAIN DRAIN WITH (3) 4X2 (1) 4X3 STUB ONLY. WILL NEED CONTINUATION TO FIXTURES. |
|
| 07/11/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 07/10/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HOURS INSPECTION CHECK #24852 (2) 2" FLOOR SINKS ON COMBINATION WASTE & VENT SYSTEM FOR MEAT CASES OK WATER TEST. 1. 2" FLOOR SINK FOR BAKERY CREAM CASE WATER TEST OK BAKERY HAND SINK WATER TEST OK ALL UNDERGROUND ONLY 1. WILL NEED TEST THRU ROOF ON ALL VENTS. |
|
| 07/07/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HOURS INSP. CHECK #5533726309 UNDERGROUND ONLY FOR 2" DRAIN FOR SIDEXSIDE LAVS BA-104 & FX215 IN BAKERY WATER TEST OK 1. THESE LAVS SHALL HAVE LONG RADIUS DRAINAGE 90 DEGREES FOR HORIZONTAL X HORIZONTAL CHANGE OF DIRECTION OUT OF WALL ON DRAIN AREAS AND BE TESTED THRU ROOF. 2. CAP EXISTING VENT BELOW FLOOR THIS AREA PRIOR TO CONCRETE. PIPE WRAP THIS PIPING OK 3" CAP + 2" CAP BELOW FLOOR FROM DEMO RESTROOM OK |
|
| 07/06/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HOURS INSP. CHECK #5533726296 4" GREASE WASTE CONTINUATION NORTH FROM 6/30/06 INSPECTION WATER TEST OK 2" SANITARY DRAIN FOR FS-2 AT 3-COMP SINK IN BAKERY ALL ABOVE OK |
|
| 06/30/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) WATER TEST 4" CONTINUATION OF GREASE WASTE INCLUDING BAKERY PROP SINK FLOOR SINK, COMBO FOR FLOOR SINK FOR CONDENSATE FOR OWNER, PER MY INITIAL ON P1-2 OK. NEED CONTINUATION FROM INITIAL 6/30/06 |
|
| 06/29/2006 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* WATER TEST NOT HOLDING. POSSIBLE LEAK AT COUPLING. BACKPITCH IN 2 PLACES. LESS THAN 1% IN OTHER AREAS AND 2% IN SOME AREAS. PROVIDE UNIFORM SLOPE THROUGHOUT. INSTALL COMBO FOR FS AT COL. 2.4/G USE THREAD SEALANT ON FCO. INSTALL 3" FCO STILL WAITING FOR LISTING OF FCO + FD FITTINGS CALL FOR INTERMEDIATE INSPECTIONS FOR VENTS AT 1. PROVIDE COOLER 2. PRODUCE AREA IN BACK ALSO AD C/O'S OF FSS. |
|
| 06/24/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* SPECIAL REQUEST INSP. PAID W/MONEY ORDER 55337260979 - GREASE WASTE IN MEAT DEPT. OK TO COVER - FOR FUTURE INSPECTIONS HAVE ALL PIPING CONTINUOUSLY SUPPORTED, WRAPPED W/FOAM WHERE PASSING THRU CONCRETE AND HAVE FDS INSTALLED. - PROVIDE THE PRODUCT LISTING FOR FCS AND FDS. |
|
| 06/23/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* PROVIDE TEST ON VTR AT PRODUCE COOLER. UNDERGROUND PIPING IN PRODUCE PREP AREA INSTALLED PER REDLINES ON PLAN, OK EXCEPT FOR PVC P TRAP ON FLOOR DRAIN (TRANSITION GLUE NOT FOR USE WITHIN BUILDING). AND GEM CAP ON DEMOED CAST IRON - PROVIDE PERM CAP. OK TO COVER EXCEPT AT LOCATION OF CORRECTIONS. WRAP PLASTIC PASSING THRU CONCRETE. INSTALL FD PROVIDE METHOD OF TRAP SEAL PROTECTION OF F.D. PROVIDE LISTING FOR USE OF PLASTIC F.C.O |
|
| 06/21/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* YOUR 3" VENT FOR COMBINATION WASTE & VENT FOR PRODUCE CASE IS OPEN 2' ABOVE PRODUCE CASE. THIS LINE SHALL BE VENTED THRU ROOF. UNTIL THIS WORK IS COMPLETED THE SEWER VENT SHALL BE CAPPED TO PREVENT THE CONTAMINATION OF THIS OPERATION FOOD STORE FROM SEWER GASES. THIS IS A SERIOUS HEALTH ISSUE. THIS IS YOUR LAST WARNING. IF ANY DRAIN OR VENT LINES ARE LEFT OPEN AGAIN YOU WILL BE REFEED AND THE HEALTH DEPT WILL BE NOTIFIED. YOUR 3" FCO AT MOP SINK IS OK, BUT I WOULD LIKE TO SEE THE PRODUCT LISTING BEFORE ACCEPTING ANY MORE OF THIS TYPE FCO. FS ON GRIDLINE C/C2 REQUIRES A CLEANOUT CAN BE INSTALLED ON VENT. 2" FS REQUIRES A VENT BECAUSE THIS INSTALLATION DOES NOT MEET THE REQUIREMENTS OF A COMBINATION WASTE & VENT SYSTEM. |
|
| 06/16/2006 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 06/15/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 06/14/2006 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* BELOW PLAN TABLE YOU HAVE AN UNCAPPED OPEN DRAIN PIPE. CAP ALL OPEN DRAIN WASTE & VENT OPENINGS! |
|
| 06/01/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HOURS INSP. CHECK #24854 -- $108.00 COMBINATION WASTE & VENT SYSTEM FOR PRODUCE LINE WATER TEST TO 10' AFF ON VERT OK |
|
| 05/25/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* AFTER HOURS INSPECTION CHECK #5532304747 $108.00 FS-2 AT FLORAL AREA UNDERGROUND WATER TEST OK WATER COUPED WITH 1/2" FOR BALOON FILL UNDERSLAB. RESTROOM WITH BREAKROOM SINK UNDERGROUND WASTE & VENT TO ABOVE TOP PLATE WATER TEST OK. 1. ALL PIPES TO BE WRAPPED PRIOR TO CONCRETE. TRAP PRIMERS OK FOR FLOOR DRAINS. 2. NEED TO SEE INSTALLK OF PRIMER VALVES. 3. WATER PIPING IN RESTROOM TO BE TESTED. IT SHALL BE SIZED TO MINIMUM 2003 UPC REQUIREMENTS LOOK AT YOUR ISOMETRIC IN THIS AREA. OVERHEAD WATER PIPING TO BE SUPPORTED PER 2003 UPC REQUIREMENTS. SEE DETAIL #4 P 1.5 4. YOU SHALL PROVIDE AIR CHAMBERS OR SHOCK STOP DEVICE FOR ALL SELF CROSSING FIXTURES. NOTE PUBLIC USE LAVS REQUIRE MAX. 110 DEGREE HOT WATER TEMPERATURE MAY BE REQUIRED. WATER HEATER CANNOT BE SOLE CONTROL OF TEMPERATURE TO PUBLIC USE LAVS. |
|
| 05/10/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* |