Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 03/28/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* PROVIDE PIPE WRAP PROTECTION THROUGH SLAB. |
|
| 03/24/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* POST ADDRESS 1. 3" UPPER TERMINAL CLEAN-OUT REQUIRES A SWEEP AT THE VERTICAL TO HORIZONTAL CHANGE OF DIRECTION. 2. TWO WAY CLEAN-OUTS MUST BE FULL SIZED ALL OTHER AREAS DWV WATER TEST OK HAVE ARCHITECT SPECIFY THAT ABS IS OK FOR USE IF ABS IS OK FOR USE, THEN YOU MAY COVER ALL AREAS EXCEPT AT NECESSARY CORRECTIONS. |