| 12/01/2006 | BUILDING - PROGRESS | Approved | PER BU FINAL | |
| 10/02/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* OK TO PROCEED |
|
| 07/25/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* OK TO PROCEED |
|
| 06/30/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* SOUTH SITE WALLS & TRASH ENCLOSURE TOP OUT OK TO GROUT. |
|
| 06/23/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* CMU COLS TOPPED OUT RFI ATTACHED |
|
| 06/20/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* OK TO PROCEED |
|
| 06/16/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* OK TO GROUT EXTERIOR COLUMNS CONTRACTOR TO FURNISH COPY OF RFI DETAIL TO BUILDING INSP. |
|
| 06/08/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* PROVIDE RFI FOR AS BUILT SADDLES OR INSTALL SADDLES PER 1/5.3 |
|
| 06/02/2006 | BUILDING - PROGRESS | Partial Approval | IVRS - Inspection :* 1ST LIFT CMV COLUMNS OK |