Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/31/2006 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 03/15/2006 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. PROVIDE CORRECT SECURING OF PIPING TO BUILDING 2. INSTALL GAS PIPING AND APPROVED PLAN 3. PROVIDE WEATHER FLASHING FOR PIPE PENETRATION THRU ROOF. 4. PROVIDE TEST GAUGE IN 1/10 POUND INCREMENTS 5. SUPPORT PIPING WITH APPROVED DEVICES & SECURE PROPERLY ON HORIZONTAL TO BUILDING. |
|
| 03/14/2006 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* |
|
| 03/07/2006 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* - GAS PIPE MUST BE STRAIGHT & ON A FIRM BED - PROVIDE MIN. 10 LB. PRESSURE TEST - PROVIDE APPROVED GAS SHUT OFF VALVES - PROVIDE SUPPORT UNDER EXPOSED GAS PIPE - PROVIDE APPROVED PLANS |
|
| 03/03/2006 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) 8:37 AM-NO ACCESS 2) HAVE AN ADULT PRESENT 7:00 AM-3:30 PM TO PROVIDE ACCESS |