Permit: T06CM00219

Parcel: 136088090


Addresses:

9620 E 22ND ST


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T06CM00219

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
12/29/2006 ENGINEERING - FINAL Approved
09/19/2006 ENGINEERING - FINAL Partial Approval -ACCESS TO VILLAGE INN MUST BE BLOCKED OFF
-ACCESS IS CURRENTLY LIMITED TO STORE FRONT-CONSTRUCTION TRAFFIC IS SEPARATE
-OKAY FOR TEMP C OF O OR FINAL AS DEEMED BY BUILDING OFFICIAL
09/18/2006 ENGINEERING - FINAL Partial Approval TENANT DUMPSTERS IN PARKING LOT
ACCESS IS LIMITED TO STORE FRONTS ONLY
CONSTRUCTION TRAFFIC IS SEPARATE
09/15/2006 ENGINEERING - FINAL Partial Approval -SITE WORK PROGRESSING
-PUBLIC ACCESS WILL BE LIMITED TO TI STOREFRONT ONLY
-ASPHALT IN PLACE FOR TI LOCATIONS
-FOLLOW UP INSPECTIONS FOR 9/18 TO VERIFY
OKAY FOR TEMP ON TI
09/13/2006 ENGINEERING - FINAL Partial Approval WALKED SITE WITH JIM CASEBOLT/JASON CAGLE W/ TL ROOF AND JOHN (PAVING GUY)
SITE IS PROGRESSING-TEMP C OF O FOR 9/19
RE-INSPECT 9/15

DISCUSSED LIMITING PUBLIC ACCESS, SEPARATING CONSTRUCTION TRAFFIC, PAVING COMPLETION, DRAINAGE COMPLETION

PAVING IN ALL PUBLIC ACCESS AREAS ALMOST COMPLETE WILL BE COMPLETE BY 9/15. ADDITIONAL PAVING WORK TO BE COMPLETE COB 9/19.