Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T06BU02973
Inspection Description - GRADING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/01/2011 | GRADING - FINAL | Approved | Approved | |
04/29/2009 | GRADING - FINAL | Correction Required | SENT EXPIRED GRADING LETTER SEE SIRE | |
06/23/2008 | GRADING - FINAL | Approved | AS BUILTS RECVD | |
03/11/2008 | GRADING - FINAL | Correction Required | GATES BEING PAINTED | |
08/01/2007 | GRADING - FINAL | Correction Required | SEE PICS 2518-2520 TALKED TO JASON GREEN ASBUILT AND SUBMITTED DRAWINGS (SEE IMAGES) ARE ACCEPTABLE FOR CHANGES TO GRADING PLAN EMAIL: From:Jason Green To:Bruce Wilson CC: Nichole Kalahar Zormeier Re: TEP Pantano Substation Bruce, I have spoken with the Engineering Inspector for this project, Nichole Kalahar-Zormeier, and we have agreed that an As-Built will be acceptable for the new 47-foot concrete header with 6" extruded curbs along the private driveway that accesses off of Lakeside Parkway. If any portion of the curb extends into the public right of way approval from TDOT is required and a revised grading plan will be needed. Nichole will require the As-Built prior to Final Inspection. I have copied her on this email so that she will have the .pdf files for her records. If you have any questions please feel free to contact Nichole or I for further clarification. Thanks, Jason Green, CFM Senior Engineer Associate Engineering Division COT Development Services *Phone: (520) 837-4929 Jason.Green@tucsonaz.gov >>> "Bruce Wilson" <bwilson@eectuc.com> 07/31/2007 2:04 PM >>> Jason, Thanks for taking my call this morning concerning the proposed fix for the erosion from the paved drive into the retention basin. I have attached a PDF copy of the plans for your review and hopefully being able to handle this additional work as an "As Built". The City Inspector for the project is Sue Damron and her phone number is 400-6609. If you have any questions or if you need additional information please do not hesitate to call or e-mail me. My land line number is 321-4625. Thanks for your time and consideration. Bruce Wilson |