Permit: T06BU02595

Parcel: 130140230


Addresses:

4220 E 22ND ST


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T06BU02595

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
03/18/2009 STORMWATER FOLLOW-UP INSP Approved
12/03/2008 STORMWATER FOLLOW-UP INSP Partial Approval WORK STARTED ON NE CORNER OF SITE

NO STORMWATER CONCERNS
11/28/2008 STORMWATER FOLLOW-UP INSP Partial Approval NO ONE ON SITE
NO CONCERNS
10/16/2008 STORMWATER FOLLOW-UP INSP Partial Approval SITE WORK CONTINUING
NO STORMWATER CONCERNS AT THIS TIME
09/29/2008 STORMWATER FOLLOW-UP INSP Partial Approval NO STORMWATER CONCERNS
DRIVEWAY CUTS ALONG 22ND ST ARE BEING MAINTAINED AND DO NOT APPEAR TO BE USED AT THIS TIME
08/15/2008 STORMWATER FOLLOW-UP INSP Partial Approval TRACK OUT CLEANED UP AND ENTRANCE/EXIT IS NOT BEING USED
08/14/2008 STORMWATER FOLLOW-UP INSP Correction Required TRACK OUT ONTO 22ND STREET

TALKED TO MIKE WILHITE-ENTRANCE WAS CLOSED-WILL BE CLOSED AGAIN AND 22ND WILL BE SWEPT
08/04/2008 STORMWATER FOLLOW-UP INSP Partial Approval CONTROLS IN PLACE ALONG 22ND STREET
07/18/2008 STORMWATER FOLLOW-UP INSP Partial Approval NO STORMWATER CONCERNS AT THIS TIME
SITE IS MOSTLY STABLE AND NO CONSTRUCTION TRAFFIC APPEARS TO BE IMPACTING COT STORMDRAIN FACILITIES
03/14/2008 STORMWATER FOLLOW-UP INSP Partial Approval SMALL AGREGATE ROCK HAS BEEN PLACED AT SCE

THIS AREA TO BE PAVED WITHIN A WEEK-THE SMALLER ROCK IS ACCEPTABLE AT THIS TIME
03/13/2008 STORMWATER FOLLOW-UP INSP Correction Required NO SCE IN PLACE
TRACK OUT ONTO COLUMBUS BLVD
02/13/2008 STORMWATER FOLLOW-UP INSP Correction Required MIKE NOT ON SITE
CONCRETE WASHOUT NEEDS TO BE SIGNED AND BERMED
12/13/2007 STORMWATER FOLLOW-UP INSP Correction Required NEEDS TO SWEEP STREET AT SCE
SCE NEEDS MAINTENANCE
WALL AT PERIMETER IN LIEU OF CONTROLS
11/08/2007 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS
10/26/2007 STORMWATER FOLLOW-UP INSP Partial Approval MET WITH MIKE
NO MAJOR CONCERNS
ON GOING MAINTENANCE CONTINUING
10/04/2007 STORMWATER FOLLOW-UP INSP Partial Approval ALL CONCERNS ADDRESSED FROM PREVIOUS INSPECTION
09/27/2007 STORMWATER FOLLOW-UP INSP Correction Required CORRECTION NOTICE 7 DAYS TO CORRECT OR RE-FEE

CONCRETE WASHOUT NEEDS TO BE SIGNED
CONTINUE WITH SWEEPING SCHEDULE (EVERY OTHER DAY-MANUAL)