Inspection History Details
Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/23/2007 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
| 01/22/2007 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* PROVIDE ACCESSIBILITY FOR INSPECTION IN ACCORDANCE WITH THE SECTION 109 IBC PROVIDE APPROVED PLANS NEED TO BE KEPT AT THE SITE OF WORK. |
|
| 01/18/2007 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* FIRST LIFT 4'0" OK TO GROUT PLUS PROVIDE (2) #4 REBAR ON EAST SIDE OF COLUMNS ONE ON EACH CELL. |
|
| 01/16/2007 | REINFORCED MASONRY PRE-GROUT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. OVERLAP REBAR ON COLUMNS 2 ON EAST SIDE OF CARPORT DO NOT COMPLY WITH MINIMUM REINFORCED STEEL OVERLAP, CORRECT AND PROVIDE INSPECTION ACCORDING WITH APPROVED PLANS. 2. PROVIDE APPROVED PLANS AND IRC (YELLOW SHEET) ON SITE. |