Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2008 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. | |
| 10/17/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor finished all corrections from NOV. | |
| 10/09/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor has only minor item to address from NOV. I explained to Mike he needed to keep up with SWPPP issues and make repairs as needed. I told Mike if the minor items are not addressed by my next inspection I will issue a second NOV. | |
| 10/08/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor has not addressed issues on correction notice dated 10/5/07. Issued Notice of Violation, contractor still needs to: 1- Clean wash out from around site. 2- Install wattle northwest corner. 3- Re-install construction entrance. Site is in violation of the stormwater ordinance 26-40. #6, 8, 5, contractor has 1 day to address items on NOV. If not will issue a Stop Work Oder. |
|
| 10/05/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Issued Correction Notice. Contractor needs to: 1- Clean wash out from around site. 2- Provide wash out area and ensure use. 3- Install wattle on northwest corner. 4- Re-install construction entrance. 5- Remove material from detention basin. Contractor given 1 day to complete items. If contractor does not address item I will issue a Notice of Violation or a Stop Work Order. Spoke to site super in regards to. |
|
| 08/22/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to tie in all controls on east side and install controls on west side a long Commerce Ct. | |
| 07/11/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to: 1- Build concrete wash out. 2- Repair construction entrance. 3- Install controls to protect basin. Spoke to site super in regards to. |
|
| 06/11/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to add SWPPP controls and stake down existing controls, also sweep street. |