Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2007 | GRADING - FINAL | Approved | All items on final punch list for building permit T06CM03791 have been completed. | |
| 08/03/2007 | GRADING - FINAL | Partial Approval | THE SITE WAS CHECKED FOR THE FINALIZATION OF THE GRADING PERMIT, THE FOLLOWING ISSUES WERE OBSERVED INCORRECT AT THE TIME OF THE INSPECTION: 1) EROSION NOTED AROUND THE BLEED PIPE LOCATED BETWEEN THE TWO BASINS, AS WELL AS AT VARIOUS LOCATIONS NOTED THROUGHOUT THE SITE ALONG THE SLOPES NEAR THE DRAINAGE WAYS AND BASINS, REPAIR ALL EROSION AS NEEDED. 2) THE SLOPE VALUES DO NOT APPEAR TO MATCH THE APPROVED SET OF PLANS FOR THIS SITE, CHECK ALL SLOPES TO MAKE SURE THAT THEY ARE 3:1 OR FLATTER PRIOR TO SCHEDULING A RE-INSPECTION OF THIS SITE. 3) THE RESEEDING OF THE DISTURBED AREAS IS NOT NOTICABLE IN SOME OF THE LOCATIONS AROUND THE BASINS. 4) A BASIN CERTIFICATION LETTER IS REQUIRED FOR THIS SITE, MINOR SIGNS PONDING WATER HAS BEEN NOTED IN THE BASINS. 5) SOME OF THE P.A.A.L. CLEARANCES HAVE BEEN NOTED LESS THAN 24' WIDE IN THE FRONT PARKING AREA ON THE NORTH END AND AT MINOR LOCATIONS OF THE SOUTHERN DRIVEWAY. |
|
| 05/22/2007 | GRADING - FINAL | Not ready for Inspection | Tried to talk to Carl site super in regards to drainage front of building. Carl was not responsive to concerns. |