Permit: T06BU01731

Parcel: 11628001L

Inspection Status: Approved

Inspection History: GRADING - FINAL

Permit Number - T06BU01731

Inspection Description - GRADING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
03/02/2007 GRADING - FINAL Approved Contractor submitted revised drawing approved by M. Flick.
02/15/2007 GRADING - FINAL Denied Contractor needs to:
1- Stabilize south slope bank. (2to1 / 1to1)
2- Install rip rap pad west scupper.
3- Stripe all ped. crossing. Per approved drawings.
4- Install channel and rip rap on north side. Per approved drawings.
5- Address erosion east side of project.
6- Install all appropriate signage.
7- Have engineer address drainage channel south side of building.
8- Remove all stormwater controls.
9- Have engineer address all changes to drawings and have approved.
10- Remove old manhole lid. East side of project.
11- Install trucated domes on HC ramps northwest corner of project.
12- Have engineer address scupper on west side, not per SD 205.
Spoke to Wally and Dennis in regards to punch list.
02/09/2007 GRADING - FINAL Partial Approval Remove all construction debris
12/21/2006 GRADING - FINAL Correction Required Contractor needs to:
1- Re-install controls a long south side of project and east side next to gate.
2- Sweep curb line and keep track out cleaned up.
3- Clean up concrete wash out around site. Provide wash out area for all subs.
Spoke to Dennis site super in regards to issues.
09/25/2006 GRADING - FINAL Partial Approval Contractor installing stormwater pipe.