Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
Permit Number - T06BU01731
Inspection Description - GRADING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/02/2007 | GRADING - FINAL | Approved | Contractor submitted revised drawing approved by M. Flick. | |
02/15/2007 | GRADING - FINAL | Denied | Contractor needs to: 1- Stabilize south slope bank. (2to1 / 1to1) 2- Install rip rap pad west scupper. 3- Stripe all ped. crossing. Per approved drawings. 4- Install channel and rip rap on north side. Per approved drawings. 5- Address erosion east side of project. 6- Install all appropriate signage. 7- Have engineer address drainage channel south side of building. 8- Remove all stormwater controls. 9- Have engineer address all changes to drawings and have approved. 10- Remove old manhole lid. East side of project. 11- Install trucated domes on HC ramps northwest corner of project. 12- Have engineer address scupper on west side, not per SD 205. Spoke to Wally and Dennis in regards to punch list. |
|
02/09/2007 | GRADING - FINAL | Partial Approval | Remove all construction debris | |
12/21/2006 | GRADING - FINAL | Correction Required | Contractor needs to: 1- Re-install controls a long south side of project and east side next to gate. 2- Sweep curb line and keep track out cleaned up. 3- Clean up concrete wash out around site. Provide wash out area for all subs. Spoke to Dennis site super in regards to issues. |
|
09/25/2006 | GRADING - FINAL | Partial Approval | Contractor installing stormwater pipe. |