Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2007 | GRADING - FINAL | Approved | Contractor completed punch list. | |
| 07/02/2007 | GRADING - FINAL | Partial Approval | Received letter from engineer in regards to drainage. | |
| 06/28/2007 | GRADING - FINAL | Partial Approval | Contractor needs to complete items 1, 2, 3, 4, and 5. Backfill around discharge weir and provide letter of certification from a Az. registered professional civil engineer. | |
| 06/19/2007 | GRADING - FINAL | Partial Approval | Final grading punch list: 1- Complete all basin work. 2- Provide letter from engineer in regards to drainage, per chapter XIV, section 14.2 (7). 3- Remove all construction debris from site. 4- Remove port-a-potty and trash dumpster from site. 5- Stabilize all areas disturbed by construction. 6- Install rip rap apron southwest corner rear of building. 7- Install gate and comple all fence work. 8- Install wheel stops for HC parking. 9- Complete basin inlet and discharge. 10- Complete all rip rap work in basin. 11- Install hardrails rear of scuppers. |
|
| 04/30/2007 | GRADING - FINAL | Partial Approval | Contractor only needs to install valley gutter, per detail 13 on C4 and strip pedestrian area on east side of building. Per Steve with Zoning and Jason Green. | |
| 02/26/2007 | GRADING - FINAL | Partial Approval | Spoke to site super in regards to side slope on east side of project. Approved drawings call for 3 to 1 slope, if slope is steeper contractor may need to rip rap. |